Converter with the control units CU240D-2
Operating Instructions, 04/2018, FW V4.9 SP10, A5E34262100B AF
245
Backing up data and series commissioning
7
Saving settings outside the inverter
After commissioning, your settings are saved in the inverter so that they are protected
against power failure.
We recommend that you additionally back up the settings on a storage medium outside the
inverter. Without backup, your settings could be lost if the inverter develops a defect.
Replacing the Control Unit without data backup (Page 293)
The following storage media are available for your settings:
●
Memory card
●
PG/PC
●
Operator panel
Note
Data backup using Operator Panels with USB connection with the PG/PC is not possible
If the inverter is connected with a PG/PC via a USB cable, you cannot backup data to a
memory card via an operator panel.
•
Disconnect the USB connection between the PG/PC and inverter before you backup data
to the memory card via an operator panel.
Carrying out series commissioning
Series commissioning is the commissioning of several identical drives.
Precondition
The Control Unit to which the settings are transferred has the same article number and the
same or a higher firmware version as the source Control Unit.
Overview of the procedure
1.
Commission the first inverter.
2.
Back up the settings of the first inverter to an external storage medium.
3.
Transfer the settings from the first inverter to an additional inverter via the data storage
medium.