3 Installation and Commissioning
B
−
15
CP 443-1 for Industrial Ethernet / Manual Part B
Release 07/2010
C79000-G8976-C223
−
06
3 Installation and Commissioning
3.1
Procedure / steps in installation
Caution
When installing the CP for use as a PROFINET IO controller, note the following
points about the power supply:
When using the CP in the central rack or in a universal rack operating as central
rack, you should not insert or remove the CP when the power is on. If you remove
the CP when the power supply is on, the CPU changes to STOP and indicates
“I/O error”.
After inserting the module with power applied, it is essential to turn the power
supply off and on again.
Note:
If the CP is operated without PROFINET IO, it is possible to insert and remove the
CP when the power is no without affecting the CPU.
Installing the CP involves the following steps.
Step
Explanation / meaning
1. Turn off the power supply when you have
configured the CP for PROFINET IO
communication.
If the CP is configured as a PROFINET IO
controller and you remove or insert the module, the
CPU assigned in the rack changes to STOP.
2. Inserting the CP: Fit in the CP onto the rack
from the top and push in at the bottom.
The CP can be plugged into all racks with slots for
P and K bus attachment.
Notice
When using the universal rack UR1 or UR2 as an expansion rack, a communication bus transceiver is
necessary!
Suitable slots in the rack:
With the exception of the slots reserved for the
power supply, the CP can be operated in all slots
with a P and K bus attachment.
3. Secure the CP with screws.
4. Turn the power supply on again.
5. Connect the CP to Industrial Ethernet over an
RJ-45 jack.
You will find examples of network attachments in
the general Part A of this manual.