Commissioning
8.2 Basic commissioning procedure
CPU 1515SP PC2 (F/T/TF)
Operating Instructions, 09/2018, A5E42603425-AA
43
8.2
Basic commissioning procedure
Step
Execution
Section
1
Requirements
2
Preparing commissioning
3
Commissioning procedure
8.2.1
Requirements
The following requirements must be met before you commission the Open Controller for the
first time:
●
The CPU 1515SP PC2 is mounted.
●
The supplied CFast card is inserted.
●
No data carriers are connected via USB.
8.2.2
Preparing commissioning
Procedure
When the requirements are met, proceed as follows with the commissioning:
1.
Connect a monitor using a DisplayPort cable.
2.
Connect a keyboard and a mouse to the CPU via USB.
Result
The Open Controller is prepared for commissioning.
8.2.3
Commissioning procedure
When you start up your CPU 1515SP PC2 for the first time, basic settings and the
administrator password are queried. The device is then automatically set up for the operating
system that is installed on the CFast card. Restart the device after the operating system has
been set up.
Note
The initial commissioning is not possible with a Multitouch panel, as the Multitouch driver is
only available after the installation of the operating system.