7
6. Connect the subscriber unit to a power source and the network. For more information, refer to
7. Seal all cable connections. For more information, refer to
Section 2.7, “Weatherproofing the Subscriber Unit”
.
8. Configure the subscriber unit. For more information, refer to
Section 3.1, “Configuring the Subscriber Unit”
.
Section 2.2
Unpacking the Subscriber Unit
The following items are included in the RUGGEDCOM WIN5237-IS package:
Item
Quantity
RUGGEDCOM WIN5237-IS Subscriber Unit
1
RUGGEDCOM WIN1010 AC Power Injector
1
Radio Frequency (RF) antenna cables, 5 m (16.4 ft) long
2
Pole/wall/tower mounting kit
1
RJ45 PoE Connector Kit
1
When unpacking the subscriber unit, do the following:
1. Inspect the package for damage before opening it.
2. Visually inspect each item in the package for any physical damage.
3. Verify all items are included.
If any item is missing or damaged, contact Siemens for assistance.
Section 2.3
Site Preparation and Precautions
Before installing the subscriber unit and or antenna(s), it is important to plan the the complete installation and
make sure the appropriate safe guards are in place.
Site Selection
Consider the following recommendations when selecting an appropriate site for the subscriber unit and
antenna(s):
• Mount the antenna(s) at the highest point possible. Reception will increase according to the height of the
antenna(s).
• Mount the antenna(s) in a place with as few obstructions as possible between the antenna(s) and the planned
service area.
• To avoid interference, mount the antenna(s) and subscriber unit as far as possible from other antenna(s) and
subscriber units.
• Keep the cable from the subscriber unit to the antenna(s) as short as possible and mount the antenna(s) as
close as possible to the subscriber unit. Using a cable longer than 2 m (6.6 ft) will result in greater loss and more
interference, as the cable will act as an antenna itself.