3. Push the link
2
through the opening in the side wall, and bolt it together with both units of
the earthing busbar.
Fig. 99:
Interconnected earthing busbar
4. Bolt together all other units of the earthing busbar of the complete switchgear assembly in
the same way.
5. Install the removed cable brackets in all panels again.
✓
The earthing busbars of the complete switchgear assembly are interconnected.
7.19 Installing the low-voltage compartment
As standard, the low-voltage compartment is pre-assembled on the associated panel. Depending
on the design of the respective panel, the low-voltage compartment can also be delivered
separately.
1. Before setting down the low-voltage compartment lead the low-voltage cables upwards out
of the panel.
2. Place the low-voltage compartment onto the roof of the associated panel. Do not damage
the low-voltage cables.
3. Bolt the low-voltage compartment onto the roof plate of the panel using 4 bolt-and-washer
assemblies M8.
4. Bolt the low-voltage compartment together with the low-voltage compartment in the
adjacent panel using 4 bolt-and-washer assemblies and nut-and-washer assemblies M8.
5. Connect the low-voltage cables according to the circuit diagram.
4x