Figure 9-2: Stool Installation Diagram
9.3 Pulling and Gland Ducted Cables
Step No.
UPS Cabinet
Battery Expansion Cabinet
Refer to
2
Pull and gland ducted cables
Section 9.3
NOTE
: It is recommended that the Ethernet cable, if fitted, is pulled through all
conduits prior to attaching the RJ45 termination jack. This ensures the
termination is not compromised in any way during the pulling procedure. See
section 9.10 for termination details
NOTE:
Sharp bends in all cables are to be avoided. A minimum bend radius of
4x the cable diameter should be observed where possible.
1.
Pull all external cables through underground ducting and up into the cabinet via
the aperture in the left of the stool by the CET plate. See section 7 for details on
external cabling.