5 Startup and shutdown
5.1 Startup
Step 1
Switch on the DC switch (optional) and DC switch in the project site. When the PV arrays provide
enough startup voltage, the LCD will enter the main interface.
Step 2
Switch on the AC switch between inverter and grid. If the alarm indicator doesn't light on, the LCD
will show "current status: standby".
Step 3
When the DC and AC supply power normally, the inverter will prepare to start. At first, the inverter
will check the inner parameters and AC grid parameters, if they are in the normal range, 60s later, the
inverter will check the insulation impedance.
Step 4
About 60s, the inverter will generate power normally. The grid connection indictor will be on and the
LCD will show: "current status: grid-connected".
5.2 Shutdown
Step 1
Switch off all switches.
Step 2