COMMISSIONING
6
6.6
Start-up for the NO
x
converter (option)
▸
Check that the cartridge is inserted.
▸
Wait for the converter warm-up phase to end (duration: approx. 15 to 30 minutes)
▸
The converter is ready for operation after the preset operating temperature is reached.
6.7
Commissioning of cabinet climate control
▸
Observe the relevant Operating Instructions and Data Sheets in the system documenta-
tion for commissioning the climate components.
▸
Adapt the settings for operating parameters / temperatures to local conditions. Other-
wise PowerCEMS100 analysis system components could fail or be damaged.
▸
Wait for a certain time (
24 hours
) after installation or initial commissioning to ensure
optimum lubrication and cooling of the control cabinet cooling unit. Refer to the specific
Operating Instructions of the control cabinet cooling unit for details on this wait time.
Installation location
The corresponding climate components are fitted on the PowerCEMS100 analysis system
depending on the planned installation location (local conditions).
The following can be used, for example:
●
Control cabinet fan (option)
●
Control cabinet cooling unit (option)
●
Control cabinet heating (option)
▸
The climate components are pre-set to the following operating parameters/temperature
values:
– Control cabinet fan / cabinet thermostat:
25 °C
– Control cabinet cooling unit:
25 °C
– Heating (optional):
approx. 15°C to 20 °C
Also see the Operating Instructions of the NO
x
converter.
Note
▸
Avoid frequent, short starts of the system cabinet cooling unit or opening the
system cabinet door frequently for short periods.
▸
Observe the minimum switch-off times when switching on the system cabi-
net cooling unit and/or the complete PowerCEMS100 analysis system.
Non-observance of the minimum switch-off times may damage the system
cabinet cooling unit.
▸
Refer to the relevant Operating Instructions of the system cabinet cooling
unit for recommended minimum switch-off time.
Refer to the relevant Operating Instructions for details on commissioning and
operation of the individual components or the wait time for the system cabinet
cooling unit.
NOTE
These settings must be adapted to local conditions.
Internal system components of the PowerCEMS100 analysis system can fail or be
damaged when operating / ambient temperatures are too low or high.