background image

Page 9

Finally, you have one of the greatest machines on earth....

Well, at least we'd like to think so - and many of our owners agree. 

Therefore, enjoy it! 

Leave us a review on our website!  

Please visit us at:  

www.ShuttleSystems.com  

1-800-334-5633

Made in the

  

USA 

Summary of Contents for MVP

Page 1: ...Page 1 Tower Installation If you discover damaged or missing parts please contact Shuttle Systems support shuttlesystems com 1 800 334 5633 9am 5pm Pacific Time ...

Page 2: ...ne of the three available Shuttle MVP models your parts may appear slightly different than those in the included images but the required steps remain the same If there is any shipping damage please take a photo of the damage and email to support shuttlesystems com or call 800 334 5633 Tools Needed 1 2 inch socket or combination wrench Allen wrench provided in Parts Bag Socket Wrench Set Typical co...

Page 3: ...will come in one box 1 Towers Towers Wings Parts Bag Rope Allen wrench Pulley Systems Head End Stand Head End It is important to become familiar with the Head End of the machine as it refers to the end of the stand the Towers will be installed ...

Page 4: ...d of the Rails Pic 1 2 3 Once the Kickplate Board and Carriage are removed turn the Shuttle MVP on its side to get access to the two feet at the Head End Stand This step is easier with two people 4 Remove the two feet on the Head End stand using a 1 2 socket and the included Allen wrench in the Parts Bag Pic 1 4 5 Position and secure the Tower Base to the exposed bolt holes and tighten the two fee...

Page 5: ...Page 5 1 1 1 2 1 4 1 5 Knee Bumpers Eye Bolts ...

Page 6: ...lts from the Head End Stand and add the wings in alignment with the now exposed bolt holes Pic 2 1 2 Using the hardware attached to the Wings tighten down fully to the MVP Rails with the lock nuts facing outwards Pic 2 2 3 Place the nut caps now exposed on the outside of the machine 2 1 2 2 2 3 ...

Page 7: ...nd attach the Towers onto the Plastic Blocks at the Head End Stand The Towers should go out from the machine Pic 3 2 3 Insert the bolts that were originally attached to the Towers through the Wings and out through the Towers Tighten once in position Pic 3 3 4 Secure the base of the Towers by tightening down the bottom bolts to the Plastic Blocks Pic 3 4 3 2 3 3 3 4 ...

Page 8: ... the rope through both Pulleys leaving the handles resting on the ground Pic 4 2 3 Located on the side of the carriage are two plastic hole inserts Remove all 4 of the plastic inserts from the carriage 2 on each side and insert the Rope Cleat Tighten down fully 4 Secure the rope by pushing the rope into the Rope Cleat The rope should not move through the Cleat Pic 4 4 4 1 4 4 4 2 ...

Page 9: ...ne of the greatest machines on earth Well at least we d like to think so and many of our owners agree Therefore enjoy it Leave us a review on our website Please visit us at www ShuttleSystems com 1 800 334 5633 Made in the USA ...

Reviews: