B---FRAME INSTALLATION
Figure 3
1.Figure 3 shows to connect the Top roof tube(No.1/No.1A),Upper curing tube(No.2/No.2A),
Middle curving
tube
(No.3/No.3A), Lower curving tube(No.4/No.4A) ,Sidewall curving tube (No.5/No.5A)and Standing leg(No.6)
with Bolt M12x50(No.23),which makes in one arch, then put the arch into tube of Base plate by Hoist, and
assemble every group of arch by turns.(see Figure 4).
Do not install the bolts on top of the truss where the fabric will rest.
Figure 4
2. Connect Purlin(No.9) to arch by using Bolt 12x100(No.24) by turns(see Figure 4),then connect the Steel
wire(No.18 and No.20) on top and side by using Clip(No.19)(see Figure 1)
Do not tighten down the nuts completely until frame is fully assembled and set in place,
the arches, the front and back panel should be assembled well on the ground before
erected into the Base plate.