Sentry Equipment Corp
Choosing a Mounting Location
Before installation, select a mounting location that provides the following:
Floor or wall must have adequate structural capability.
Anchor location and design is adequate.
Operation and maintenance space is sufficient.
Cooling water is available.
Floor drain is accessible if required.
Mounting surfaces are flat/level and at appropriate height.
There is adequate light for operation and maintenance.
For optimum equipment reliability and installation, the area should:
Be free from mechanical vibration.
Be free from corrosive media.
Have a normal ambient temperature near 75-80°F (24-27°C) with minimal variation.
Be free from strong heat radiation.
Provide adequate support and anchoring to minimize gravity and thermal loads on the
connections and to minimize any vibration effect.
If installing over drywall, the panel must be secured to the wood studs using 3/8 inch
(M10) hardware.
Connecting Sample Lines
Improper connection sizing will result in an unsafe condition .
Improper cell holder locations can adversely affect the operation of the unit .
Connect the sample inlet and outlet at the bottom of the panel. Both connections are
1/4" tube compression fittings. Clean and deburr all connecting pipe and tubing before
installing.
Â
NOTE
Samples supplied to the DCCP should be cooled to 77°F (25°C) and pressure controlled by either
a backpressure regulator or head cup to maintain a constant sample flow rate .
If you have purchased the DCCP without factory mounted cell holders, refer to Figure 3
for proper cell mounting and drain piping configurations. Cell holder(s) must be installed
in an orientation that maintains the water level in the degas chamber near the cross over
section of the degas chamber. To accomplish this, the sample outlet from the panel must
be even with the cross over section of the degas chamber. It is important to follow these
instructions to obtain accurate conductivity measurements.