WWW.SEAGULLMODELS.COM
15
15
When cutting through the covering to re-
move it, cut with only enough pressure to only
cut through the covering itself. Cutting into
the balsa structure may weaken it.
4) Slide the vertical stabilizer back in-
place. Using a triangle, check to ensure
that the vertical stabilizer is aligned 90º
to the horizontal stabilizer.
90º
Vertical
Stabilizer.
Horizontal
Stabilizer.
Epoxy
Epoxy
5) When you are sure that everything is
aligned correctly, mix up a generous
amount of Flash 30 Minute Epoxy. Ap-
ply a thin layer to the mounting slot
and to bottom of the vertical stabilizer
mounting area. Apply epoxy to the bot-
tom and top edges of the filler block and
to the lower hinge also. Set the stabilizer
in place and realign. Double check all of
your measurements once more before
the epoxy cures. Hold the stabilizer in
place with T-pins or masking tape and
remove any excess epoxy using a paper
towel and rubbing alcohol. Allow the
epoxy to fully cure before proceeding.
ELEVATOR - RUDDER PUSHROD
HORN INSTALLATION.
1) Install the elevator control horn using
the same method as with the aileron con-
trol horns.
2) Position the elevator control horn on
the both side of elevator.
M2 lock nut.
M2 clevis.
8mm