724VK2 Verification Tester

Operation Instructions

Description

The SCS 

724VK2

 

Verification Tester is used to 

perform periodic testing of the SCS 

724

 Workstation 

Monitor.  The Verification Tester allows the customer 

to perform NIST traceable calibration verifying that the 

724

 Workstation Monitor is operating within tolerances.  

Using the 

724VK2

 takes only a few minutes and is 

designed to be used on the shop floor at the workstation 

to virtually eliminate downtime.

Frequency of recalibration should be based on the 

critical nature of those ESD sensitive items handled and 

the risk of failure for the ESD protective equipment and 

materials.  In general, SCS recommends that calibration 

be performed annually.

June 2015

The SCS 

724VK2

 Verification Tester can be used with 

the following items:

Item

Description

724

Workstation Monitor

724 W/O-PS

Workstation Monitor, without Power 

Adapter

724K-WM10

Workstation Monitor Kit

724K-WM11

Workstation Monitor Kit

Packaging

1  Verification Tester

1  Certificate of Calibration

Operation

Test Voltage 9 Volts and Resistance Selection 10 

Megohms

Set the 724 Workstation Monitor’s test voltage to 9 volts 

and its resistance limit to 10 Megohms.

1. 

Insert the Verification Tester’s stereo plug into the 

monitor’s remote jack #1.

 

2. 

Select “1.5M LOW” with the Verification Tester’s 

rotary switch.  The monitor’s green OK 1 LED 

should illuminate, and the yellow L LED should 

flash.  The audible alarm should not sound.

3. 

Select “1.5M PASS” with the Verification Tester’s 

rotary switch.  The monitor’s green OK 1 LED 

should illuminate.  The audible alarm should not 

sound.

4. 

Select “10M PASS” with the Verification Tester’s 

rotary switch.  The monitor’s green OK 1 LED 

should illuminate.  The audible alarm should not 

sound.

5. 

Select “10M HIGH” with the Verification Tester’s 

rotary switch.  The monitor’s red H LED should 

illuminate, and the audible alarm should sound 

continuously.

6. 

Repeat steps 1-5 for jack #2 on the remote.  The 

audible alarm will chirp when jack #2 fails high.

Made in the

United States of America

 USER GUIDE TB-9012

Figure 1.  SCS 

724VK2

 Verification Tester