INSTALLATION, MOUNTING AND OPERATING INSTRUCTIONS 

 

Mounting information  

 

 

Construction subject to change 

 

No return possible 

Version: 2018-11-14 | Page 5 

MOUNTING INFORMATION 

INSTALLATION IN SOLID WALLS 

 

 

Installation in solid walls (shaft walls, shafts, ducts and fire 
walls) made of, for example concrete, masonry according 
to EN 1996 or DIN 1053; solid plaster board walls according 
to EN 12859 or DIN 18163; apparent density ≥ 450 kg/m³ 
and wall thickness W ≥ 150 mm. 

 

Installation with horizontal damper leaf.  

 

Circumferential  gaps  "s"  must  be  filled  completely  with 
mortar of categories M2.5 to M15 according to EN 998-2, 
NM II to III DIN V 18580 (previously: MG II to III according 
to  DIN  1053)  or  fire  protection  mortar  of  the  correspon-
ding grade or with concrete suitable for the wall type. The 
minimum gap size s

min

 is 50 mm. If the fire damper is in-

stalled during the construction of the wall, the gaps "s" can 
be omitted. The mortar bed depth has to be designed ac-
cording to the minimum wall thickness and may not be less 
than this thickness. 

 

The distance between the fire dampers must be min. 200 
mm. 

 

Distance to the bearing adjacent components (wall / solid 
ceiling) is minimum 75 mm. 

 

INSTALLATION IN SOLID CEILINGS 

 

 

Installation in solid ceilings, for example made of concrete, 
foam  mortar;  apparent  density  ≥  500  kg/m³  and  ceiling 
thickness D ≥ 150 mm. 

 

Installation with full mortar lining (circumferential gaps "s" 
must be filled completely with mortar of category M15 ac-
cording to EN 998-2, NM II DIN V 18580 (previously: MG III 
according to DIN 1053) or fire protection mortar of the cor-
responding grade. The minimum gap size smin is 50 mm. If 
the fire damper is installed during the construction of the 
ceiling, the gaps "s" can be omitted. The mortar bed depth 
has to be designed according to the minimum ceiling thick-
ness and may not be less than this thickness.   

 

The distance between the fire dampers must be min. 200 
mm. 

 

Distance to the bearing adjacent components (wall) is mi-
nimum 75 mm. 

 

Installation in solid wall 

 

 

 

 
 

 

Installation in solid ceilings 

 

 
 
 
 
 

Figure 4: Installation in solid walls and ceilings 

 

CONNECTION OF VENTILATION DUCTS 

 

The fire dampers must be connected to the ventilation ducts 
of the ventilation system either on one or on both sides. For 
one-sided  connections,  finishing  protective  grating  made  of 
non-combustible material (EN 13501-1) must be provided on 
the  respective  opposite  sides.  The  fire  dampers  can  be 
connected  both  to  non-combustible  and  combustible 
ventilation ducts.   
The  local  regulations  or  national  standards  on  ventilation 
systems (in Germany e.g. LüAR) apply. 
No inadmissible forces may affect the fire damper and space-
enclosing  components  especially  in  case  of  fire  and  impair 
their  fire  resistance  time.  The  required  expansion  joints 
(flexible  connecting  pieces)  must  be  designed  as  flammable, 
elastic  connecting  pieces  made  of  at  least  standard 
inflammable materials (EN 13501-1) and installed between the 
fire  damper  and  ventilation  duct.  Flexible  part  of  the 
connecting  piece  (polyester  fabric)  must  have  the  minimum 
length  of  l

min

  =  100  mm  in  the  mounted  state,  this  gives  a 

mounting dimension of approx. L = 160 mm. As an alternative, 
instead  of  installing  flexible  connecting  pieces,  flexible 
ventilation  ducts  made  of  aluminium  can  be  connected. 
Ventilation ducts must be suspended separately. 

Summary of Contents for BSK-EN

Page 1: ...dimensions 3 Mounting information 5 Installation information 6 Technical data 7 Accessories 9 Legend 14 Specification text 15 Identification label 17 Maintenance or functional test 18 Certificate of...

Page 2: ...be connected both on non combustible and com bustible ventilation ducts MODELS Housing made of galvanised sheet steel cold and hot leakage requirements according to EN 1366 2 are met u sing circumfer...

Page 3: ...50 650 700 700 750 750 800 800 900 1000 1100 1200 1300 1400 1500 Table 1 Available sizes Housing length L 500 mm All width and height dimensions can be combined Release device always on H side On requ...

Page 4: ...cting piece RS Pipe connecting piece a 50 mm Minimum distance between the front edge of the open damper leaf and the fi nishing protective grating ASG flexible connecting piece FS or pipe connecting p...

Page 5: ...otection mortar of the cor responding grade The minimum gap size smin is 50 mm If the fire damper is installed during the construction of the ceiling the gaps s can be omitted The mortar bed depth has...

Page 6: ...hey must be created in the direct vicinity in the connected ventilation ducts Inspection o penings are not available therefore they must be created in the direct vicinity in the connected ventilation...

Page 7: ...LWA dB A KF1 LWA2 dB A LWA1 dB A x KF2 LWA Abst1 dB A LWA1 dB A KF3 LWA1 Abst2 dB A LWA2 dB A KF3 p1 p x KF4 p2 p1 x KF5 200 3 1 05 7 2 15 1 66 250 3 1 07 7 1 8 1 69 300 2 1 09 7 1 55 1 72 350 2 1 10...

Page 8: ...3 40 1 41 8 45 4 49 0 52 5 56 1 59 6 63 2 66 7 Table 4 Weight table kg FREE CROSS SECTION Free cross section m2 Width mm 200 250 300 350 400 450 500 550 600 650 700 750 800 900 1000 1100 1200 1300 140...

Page 9: ...VT 1 Pipe connecting piece type RS 1 1 Standard model galvanised sheet steel powder coated RAL 9010 pure white and DD coating RAL 7035 light grey possible LIMIT SWITCH TYPE ES Electric limit switch fo...

Page 10: ...sition is possible in the de energised state It is unlocked manually On site function control is possible by means of the control key of BAT or BAE72B S Spare parts Temperature fuse for temperature in...

Page 11: ...dimensions BSK EN with B10 B11 approx 102 mm BSK EN with B20 B21 approx 106 mm BSK EN with B30 B31 approx 120 mm Figure 12 Damper dimensions 200 225 250 275 300 325 350 375 400 450 500 550 600 650 700...

Page 12: ...IEC EN II protective insulation Degree of protection IEC EN IP54 Ambient temperature Normal operation 30 55 C 30 50 C Storage temperature 40 55 C 40 50 C Ambient humidity 95 r H non condensing Table...

Page 13: ...ard flammable according to EN 13501 1 with welded lip seals sealing degree C according to EN 13180 EN 1507 temperature resistant from 20 to 80 C Flexible part of the connecting piece polyester fabric...

Page 14: ...he flow generated noise adjusted for diffe rent values of B mm in the model with finishing protective grating ASG KF2 dB A A weighted sound power level of the flow generated noise adjusted for diffe r...

Page 15: ...eft Unless specified otherwise in the order details the mechani cal model Right and fusible link with trigger temperature 72 C is supplied Alternative models or accessories at an extra charge select a...

Page 16: ...80 C Flexible part of the connecting piece polyester fabric must have a length lmin of 100 mm when mounted this gives an installation dimension of approx L 160 mm The required equipotential bonding mu...

Page 17: ...to change No return possible Version 2018 11 14 Page 17 IDENTIFICATION LABEL 1035 13 SCHAKO Iberia S L Pol Ind R o G llego Calle B nave 3 E 50840 San Mateo de G llego Zaragoza 14 ESPA A 01 01 DoP BSK...

Page 18: ...h into the swivelling range of the damper leaf and hand lever There is a risk of injury The fire damper must close automatically 1 1 3 Test of the snap in locking device Pull the disc pos 1 at the han...

Page 19: ...r Press switch pos 1 on the thermoelectric trigger device pos 2 thus the spring return actuator is disconnected from the power supply pos 3 alternatively interrupt on site power supply Fire damper mus...

Page 20: ...______________ The following function steps have been carried out according to the documents Installation mounting and operating instruc tions before commissioning Next functional check in ___________...

Page 21: ...4 Page 21 Functional test protocol for fire dampers Cons no ____________________ Defects found during the test on _____________________ Sluggishness due to soiling Any remaining mortar must be removed...