COPPER PIPE INSTRUCTIONS

1.) Follow the same instructions in 

steps 1-6

 for PVC, CPVC and PEX pipe. 

Use Chart B for Copper

2.) Instead of a single coil wrapping around the pipe, a second one is added for copper pipe.

3.) YOU MUST KEEP THE SECOND WRAPPING IN THE SAME DIRECTION AS THE FIRST!  Wrap 

right over the top of the first layer continuing in the same wrapping direction as the first layer – 
clockwise or counterclockwise.  This second layer must also be tight and touching the prior wrap.  

(Figure C)

4.) Wrap a third cable tie around the pipe and both wires.  

Pull the cable tie tight.  (

Figure D)

 

5.) Follow same instructions in 

steps 7-8 

for PVC, CPVC and PEX pipe.

ACTIVATING THE SYSTEM

1.) Once the power unit has been installed and the pipe has been wrapped, insert the connector end of the 

AC power adaptor into the power unit. (See 

Illustration A

 on page 5)

2.) Plug in the transformer end of the cord into a 110-volt electrical outlet.

3.) Operation of the 

ScaleBlaster

 SB-75 system can be confirmed by observing the illumination of the 

LED indicator located on the face of the power unit. Power on - green light on far right side will stay 
lit 

(Figure E)

. When pipe is wrapped and unit is turned on the far right light will stay lit and the other 

lights will oscillate back and forth 

(Figure F)

.

        

MAINTENANCE

The best feature of the 

ScaleBlaster

 SB-75 is that there is NO MAINTENANCE REQUIRED. No salt, 

batteries, moving parts or costly repairs. Just check the LED light for proper operation. 

Figure C

Figure D

SB-75

* inside dimensions

Wrap Requirement

COPPER pipe*

Pipe Size*

1/2”
3/4”

1”

1 1/4”

Layers  /  Wraps

 / 50 wraps

Double** / 50 wraps
Double** / 45 wraps
Double** / 40 wraps

Double**

Chart B

7

Figure E

Figure F

Power

Indicator

Signal

Indicators

(** Example - Double/50 wraps is a 

total of 100 wraps. 50 wraps on first 

layer and 50 on second layer.)

Never under wrap or over wrap the coil.

Summary of Contents for SB-75

Page 1: ...SB 75 Installation Operation Manual Residential Use Indoor Installation The eco friendly solution to hard water...

Page 2: ...Tech part CET 0978 3 Signal Cable 46 and four 4 nylon cable ties 4 Warranty Card 5 Extended Warranty Card 6 Installation operation manual 1 2 3 6 4 5 For indoor use only The ScaleBlaster unit can be i...

Page 3: ...pipe size place a ruler in front of the pipe and measure the outside diameter Use Table 1 to determine the size of the pipe The actual pipe size is always rated by the inside dimensions of the pipe A...

Page 4: ...ain water shutoff valve water going to house Z 115 VAC power supply included Important For best results wrap signal cable on a straight section of pipe of 12 or more Keep the signal cable as far away...

Page 5: ...ng screws for the type of surface the unit will be mounted on We recommended a number 8 screw TO COIL TO COIL 5VDC 3A Terminal Block Terminal Block Holes To get wire into terminal block holes twist ba...

Page 6: ...o the power box Trim excess cable to length 8 Carefully strip the outer plastic shield from the end of the signal cable leaving1 4 to 3 8 of bare cable Twist the bare cable and insert the end in the o...

Page 7: ...unit See Illustration A on page 5 2 Plug in the transformer end of the cord into a 110 volt electrical outlet 3 Operation of the ScaleBlaster SB 75 system can be confirmed by observing the illuminati...

Page 8: ...asted water or batteries to change Best of all you are protecting the environment Allow up to 90 days to realize the full effects Initial descaling may make things worse for awhile especially in the d...

Reviews: