CHANGE OF COMPRESSOR DELAY TIME
The delay time of high and low stage side compressor can be changed to reduce the load on the power
line and to facilitate the start-up (reset) of the freezer after power failure.
The example in the table is based on the assumption that the delay time is changed to 4 minutes.
(The delay time is set in 2 minutes at the factory.)
Note:
• The delay time should be the same for high stage side and low stage side compressors.
• The setting range for delay time is between 2 and 15 minutes. The cool down of chamber temperature
may be slow when the setting of delay time is over 5 minutes, depending on the installation environment.
There is no need of changing the delay time when the capacity of power source is adequate.
Table 8. Changing procedure for delay time (change from 2 minutes to 4 minutes)
Description of operation
Key operated
Indication after operation
1
----
The current chamber temperature is
displayed.
2
Press numerical value shift key for
5 seconds.
The first digit is flashed.
3
Set the figure to F05 with the
numerical value shift key.
When pressed, the figure of settable
digit changes.
4 Press SET key.
SET
The current delay time is displayed.
The first digit is flashed.
5
Set the figure to 004 with the
numerical value shift key.
When pressed, the figure of the first
digit changes.
6 Press SET key.
SET
The delay time is memorized and
the current chamber temperature is
displayed.
• The compressor starts to operate with the delay time set by the above procedure at the time of power on
or after power failure. However, the start up of the low stage side compressor is affected by the
chamber temperature and the cascade condenser temperature. The delay time varies depending on
how they meet the start up conditions.