INSPECTION AND HANDLING
Packing
Each section of the PureWave AVC is shipped fastened to a wood
skid. A plastic liner has been inserted underneath the section to pre-
vent water or debris from entering the bottom during shipping or han-
dling. The sections should be left on their skids with the liners intact
until just prior to installation on the pad.
Inspection
Examine the shipment for external evidence of damage as soon after
receipt as possible, preferably before removal from the carrier's con-
veyance. Check the bill of lading to insure that all shipping skids,
crates, and containers listed thereon are present.
If there is visible loss and/or damage:
1. Notify the delivering carrier immediately.
2. Ask for a carrier inspection.
3. Note condition of shipment on all copies of the delivery receipt.
4. File a claim with the carrier.
If concealed damaged is discovered:
1. Notify the delivering carrier within 15 days of receipt of shipment.
2. Ask for a carrier inspection.
3. File a claim with the carrier.
Also notify S&C Electric Company in all instances of loss and/or
damage.