Checking and Testing Operations
E-
28
To complete the installation, perform the following checks and tests to
ensure that the air conditioner is operating correctly.
Review all the following elements in the installation :
◆
Piping connection tightness to detect any gas leakages
◆
Connecting wiring
◆
Heat-resistant insulation of the piping
◆
Drainage
◆
Earthing wire connection
◆
Correct operations (follow the steps below)
Check the power supply.
◆
Compressor power supply : L1(R)-Red, L2(S)-White, L3(T)-Black
Be careful about the cables so that they will not be mixed up.
◆
220-240V power supply : L, N (Single phase cable)
1
Connect the outdoor unit to your computer where the provided software is
installed, then power the outdoor unit on.
4
How to Test Operations
Check the indoor unit(s).
2-1 Check that you have connected the power and communication
cables correctly. (Communication cables should be connected with
F1 and F2 terminals)
- If the power cables and communication cables are mixed up or
connected incorrectly, the PCB will be damaged.
2-2 Ensure the address of indoor units.
- Choose appropriate address between 0 and F.
- Each indoor unit must have different address.
2-3 Check the thermistor sensor, drain pump/hose, and electronic
expansion valve are connected correctly.
2
Check the outdoor unit(s).
3-1 Check how many indoor units are installed and the number of
indoor units registered on the rotary switch.
3-2 Check the DIP switch is at proper position.
3
If the outdoor unit is powered on, it will start tracking to check user's
option(s) and number of indoor unit. It takes about 20 seconds.
- At this time, the SEG 1 and 2 on outdoor unit PCB display the number of
indoor unit registered and the SEG 3 and 4 display the number of
indoor units which responded.
5