14-7 Installation Diagram of Indoor Unit and Outdoor Unit
14-7-1 Air-Purge Procedure
1) Connect each assembly pipe to the appropriate
valve on the outdoor unit and tighten the flare nut.
3) Open the valve of the low pressure side of
manifold gauge counter-clockwise.
4) Purge the air from the system using vacuum
pump for about 10 minutes.
– Make sure that pressure gauge show
-0.1MPa(-76cmHg) after about 10 minutes.
– This procedure is very important in order to
avoid gas leak.
– Turn off the vacuum pump.
– Close the valve of the low pressure side of
manifold gauge clockwise.
– Remove the hose of the low pressure side
of manifold gauge.
7) Check for gas leakage.
- At this time, especially check for gas
leakage from the 3-Way valve’s stem nuts,
and from the service port cap.
2) Connect the charging hose of low pressure side
of manifold gauge to the packed valve having a
service port as shown at the figure.
5) Set valve cork of both liquid side and gas side of
packed valve to the open position.
6) Mount the valve stem nuts and the service port
cap to the valve, and tighten them at the torque of
183kgf.cm with a torque wrench.
A
B
C
D
Outdoor unit
Indoor unit
Gas pipe side
Liquid pipe side
Vacuum Pump
A
(gas)
B
(liquid)
Valve stem
Stem cap
24437A(1)_1 1/16/05 9:58 PM Page 12-36
Summary of Contents for AS09HPB
Page 30: ...MEMO Samsung Electronics 5 4...
Page 34: ...MEMO Samsung Electronics 5 8...
Page 35: ...Samsung Electronics 5 9 5 4 Ass y Control Out AS09BPAX DB93 03450B AS12BPAX DB93 03450A...
Page 80: ...MEMO 12 23 Samsung Electronics...
Page 84: ...Block Diagram 13 4 Samsung Electronics DC_LINK CAP B D DIODE IPM OUTDOOR FAN SMPS IGBT...
Page 95: ...MEMO Samsung Electronics 14 11...