50
English
Ins
tallation
Step 4.3 Performing final check and
trial operation
1
Check the following:
•
Strength of the installation site
•
Tightness of pipe connection to detect gas leak
•
Electric wiring connection
•
Heat-resistant insulation of the pipe
•
Drainage
•
Grounding conductor connection
•
Correct operation (Take the following steps.)
2
Press the
(Power) button on the remote control to
check the following:
•
The indicator on the indoor unit lights up.
•
The airflow blade opens and the fan gears up for
operation.
3
Press the
(Mode) button to select Cool mode. Then
take the following sub-steps:
•
In Cool mode, use the Temperature button to set
the set temperature to 16 °C.
•
Check whether, approximately 3 to 5 minutes later,
the outdoor unit starts, and a cool air blows out.
•
After 12 minutes of stationary condition, check the
indoor unit air treatment.
4
Press the
(Air swing) button to check whether the
airflow blades work properly.
5
Press the
(Power) button to stop the trial
operation.
Pumping down refrigerant
Pump-down is an operation intended to collect all the
system refrigerant in the outdoor unit. This operation
must be carried out before disconnecting the refrigerant
tubing in order to avoid refrigerant loss to the
atmosphere.
1
Shut off the liquid valve with the Allen wrench.
2
Turn on the air conditioner in cooling with fan
operating at high velocity. (Compressor will
immediately start, provided 3 minutes have elapsed
since the last stop.)
3
After 2 minutes of operation, shut the suction valve
with the same wrench.
4
Turn off the air conditioner and switch mains supply
off.
5
Disconnect tubing. After disconnection, protect valves
and tubing ends from dust.
CAUTION
•
Compressor damage may occur if the compressor is
run at a negative suction pressure.
Pumping down for removing the product
1
Hold down the
(Power) button on the indoor unit
for 5 seconds. Beep sounds immediately to indicate
that the product is ready for pump down procedure.
2
Let the compressor run for more than 5 minutes.
3
Release the valve caps on High and Low pressure
side.
4
Use L-wrench to close the valve on the high pressure
side.
5
After approximately 1 minute, close the valve on the
low pressure side.
6
Stop operation of the air conditioner by pressing
the
(Power) button on the indoor unit or remote
control.
7
Disconnect the pipes.
1
2
Gas service port
<Low pressure>
Liquid service port
<High pressure>
1 minute
Off
DB68-06039A-00.indd 50
5/25/2016 7:09:00 PM