EB 2559 EN
25
Start-up and operation
6.4
Starting up the plant
Î
Î
Start up the regulator after mounting all
parts.
Î
Open the shut-off valves slowly prefera
-
bly starting from the upstream pressure
side.
Î
Fill the plant
slowly
with the process me
-
dium. Avoid pressure surges.
6.3
Operation
The regulator is ready for use when mount
-
ing and start-up have been completed.
Risk of burn injuries due to hot or very cold
components and pipelines.
Depending on the process medium, regula-
tor components and pipelines may get very
hot or cold and cause burn injuries.
Wear protective clothing and safety gloves.
WARNING
!