7.

 

Repeat  the  roof  panel  assembly  for  the  “D2”  (roof)  panel  on  the  remaining  “B-A-B”  (corner-end-
corner) assembly. 

8.

 

Inspect  the  alignment  of  the  “C”  (access)  panels  during  assembly.    Verify  that  their  removal  and 
replacement allow adequate space and positioning with the adjacent panels prior to attaching brackets 
to the concrete. 

9.

 

Place the Inner Roof Connection Bracket under the “D1-D2” 2x4 panel connection on the inside and 
then fasten it into place (Fig. 2E) using Hex Head Screws. 

 

FIG. 3 

10.

 

Complete the bracket and clip installations in the following steps on one side before moving on to the 
other side of the enclosure.  Fastening each anchoring bracket will require two (2) Hex Head Screws 
installed first and then one (1) Anchor per bracket installed last.  Fastening each Inside Roof Clip will 
require one (1) Hex Head Screw per clip. 

11.

 

Attach Outside Corner Anchoring Brackets (small) at both “A-B” (corner) assemblies on the first side 
of the enclosure (Fig. 2A) oriented as shown in the Enclosure Plan View, and then fasten them to the 
concrete. 

12.

 

Attach Inside Anchoring Brackets (large) to the “B” (corner) panel studs at the bottom, inside on the 
first side of the enclosure (Fig. 2B) oriented as shown in the Enclosure Plan View, and then fasten them 
to the concrete. 

13.

 

With  the  “B”  (middle)  panel  aligned  in  the  space  between  the  “C”  (access)  panels  allowing 
approximately a 

3

/

16

” gap between panels, install Inside Anchoring Brackets (Fig. 2B) at the bottom of 

the “B” (middle) panel along the first side of the enclosure. 

14.

 

Insert Inside Roof Clips into the “D#” (roof) panels at the “B” (side) panel studs (Fig. 2C) along the 
first side of the enclosure and then fasten them in place. 

15.

 

Repeat these bracket and clip steps on the other side.  Note that all provided anchoring brackets and 
Inside Roof Clips must be installed for the enclosure to withstand strong winds. 

16.

 

Install Roof Cover Plates on the “D1-D2” seam (Fig. 2D) using two (2) Hex Head Screws per plate. 

17.

 

Provide a ground-fault interrupter device in all electrical circuits per all applicable codes.  Install the 
heater(s) as per the manufacturer’s instructions and governing local and national codes. 

18.

 

For  maximum protection,  it  is  suggested  that the  area  between  the  bottom  of  the  enclosure  and  the 
concrete  base  should  be  caulked  except  for  the  “C”  panels.    DO  NOT  CAULK  THE BOTTOM  OF 
THE “C” PANELS. 