background image

38mm

38mm

38mm

8. Coverstrips, bargeboards and finials

Fit a coverstrip into each corner, attach using 3 x 38mm nails per strip. The remaining three are used to cover the panel joins on each side and back, attach using 3 x
38mm nails per strip.Attach bargeboards at the front so that the top edge is flush with the roof line and the two boards meet evenly in the middle secure using 3 x 38mm
nails per board. Repeat for the bargeboards on the back. On the front attach a finial centrally over the join between the bargeboards use 2 x 38mm nails. Repeat for the
finial on the back.

We constantly improve the quality of our products,
occasionally the components may differ from the
components shown and are only correct at time of
printing. We reserve the right to change the
specification of our products without prior notice.

If in doubt of any aspect regarding the assembly, use or safety of your building please contact us :

Help Line (Normal Office Hours)  01829 261121

ROWLINSON GARDEN PRODUCTS LIMITED
Green Lane 
Wardle Nr. Nantwich
Cheshire
CW5 6BN

25mm

10. Glazing

It is recommended that a waterproof sealant is applied around the edge of the glazing before fitting. From the outside of the building fit the acrylic window into the plastic
cill strip, fix the window in place with the wooden window beading strips at each side and the top using 3 x 20mm nails per beading strip.Add the window surround coverstrips
as shown using 3 x 38mm nails for each strip.

38mm

38mm

Ensure the right door has
the towerbolt mounting
blocks

22mm

22mm

19mm

22mm

19mm

9. Fitting the door

Position the doors in the opening and secure each door in place with 3 T-hinges and 7 x 25mm screws per hinge as shown below. On the inside of the right-hand door
secure the tower bolts to the mounting blocks using 4 x 19mm round head screws per bolt. With the doors shut, position a door coverstrip so it overlaps both doors
and is flush at the top of the doors, secure only to left-hand door using 3 x 22mm screws. In the same way fix the other door coverstrip flush to the bottom of the door.
Fit the hasp and staple between the 2 coverstrips using 7 x 19mm round head screws as shown below. Position the turn button just above the left-hand door secure to
the apex panel using 1 x 22mm screw.

Window frame

Window panel 

Plastic beading

20mm

38mm

2008 © Rowlinson Garden Products Ltd

Important information - retain for future reference

To 

VALIDATE

the guarantee, shiplap buildings come ready stained but this is only a preparatory treatment the building must be properly treated with a recognised

external wood preserver 

WITHIN 3 MONTHS

of assembly and 

RE-TREATED ANNUALLY 

thereafter.

Adequate provision must be made to ensure ground contact is avoided and air is able to circulate underneath the building. Placing the building on a concrete pad or slab
base is acceptable provided that the building is not allowed to sit in pooled water during wet conditions. If the building is to sit on soil or grass it

MUST

be erected on

additional pressure treated wooden 50mm x 50mm or similar bearers

(These are not supplied in the kit).

Rowlinson Garden Products recommend using pressure treated bearers with all buildings on any type of base

.

Timber Information.

As timber is a natural material, there are certain weather conditions that may affect the materials properties. In times of excessive dry spells the material may lose
some of its internal moisture causing a certain degree of shrinkage on a panel and in periods of excessive rain there will be a certain amount of swelling throughout
the wooden panels.This process can not be avoided. If you have problems with certain boards shrinking in dry spells try to decrease the amount of direct sunlight on
the building or the amount of air passing over the building. During hot spells spray water directly onto the panels with the aid of a garden hose.

Reviews: