OPC90 Server
Select the current set (SET_01 to SET_04) to be defined using the list box at th
bottom right of the dialog. The current point definition for that set is displayed in
the large list box. The point number and name is displayed. Click on a poin
number to be edited. Its point number and name are displayed at the bottom of
the dialog. Type in the point name and click the “Set” button to define that point.
Use the tab key to signify entry of a new value. Click the “Delete” button to
undefined the selected point. Point names must be unique within each set. SOE
point definition can also be accomplished using the OPC90 import feature.
e
t
onsult the “CSV file format” section for specific information on how to define
cted
.3.8 Priority
run.
C
SOE point names.
5.3.7 Properties
Select “Edit->Properties” to edit the current definitions setup for the sele
device, group or block. The appropriate properties dialog will be displayed based
on whether the device, group or block is the last selected database entity.
5
Select “Edit->Priority” to edit the default process priority that OPC90 will
When this menu item is selected the following dialog is displayed:
As can be seen by this dialog, available priority selections are “Normal”, “High”
nd “Realtime”. OPC90 switches itself to the new priority as soon as the
selection is made. It is not necessary to exit OPC90 and run it again for a new
a
The RoviSys Company
Version 7.0
Page 23