5A. INSTALLATION INSTRUCTIONS 

5A.4 Installation of PEX-tubing 

Start the tubing installation by connecting 
the PEX tubing to the manifold. Loops can 
be pre-cut if you have figured the correct 
leader length (from the manifold to the 
actual heated area) when designing the 
system with our software. The Radiant 
Heating Tubing Requirements Report will 
give you the information to cut the loops 
from full rolls of tubing with the least 
amount of waste. 

Install the tubes by unrolling the coil and 
stepping the tubes into the tracks in the 
panels. Use hard shoes or a wooden piece 
on top of the tubes in order to fasten the 
tubes in the tracks. Be sure to use a block 
when using a hammer or mallet to set the 
tubing to avoid denting the aluminum 
surface. Follow the loop layout you have 
planned and connect the return tube to the 
manifold. It is very important that the tubes are snapped down completely into the tracks. 
When installing the tubing in the radius panels it is important to pull the tubing tightly around the 
bends. This will allow a space for tubing expansion during operation and greatly decrease the 
chance of noise during operation. When laying the tubing into the transition pieces we 
recommend using a bead of silicone adhesive to secure the tubing because the tubing is loose 
in these pieces. We recommend installation of the panel and tubing when ambient 

temperatures are above 40°F (4.5°C). 

5A 

Summary of Contents for RADIANT PANEL SYSTEM

Page 1: ...5A RADIANT PANEL SYSTEM PLANNING INSTALLATION MANUAL rev ROTH HEATING SYSTEMS ...

Page 2: ...It is ideal for retrofit systems but it s also great for new construction when you don t want the weight expense or water problems of lightweight concrete The efficient design of the system heavy gauge full face aluminum sheet on top and EPS insulating foam on the bottom focuses the heat exactly where you want it directly under the finished floor so that the system can run at the lowest temperatur...

Page 3: ...ld locations We also recommend installing tubing in every track to achieve the best heat distribution Try to plan the pattern so that the Master Panels are aligned to allow the loop supply to run along the outer wall If installing a wood floor over the panel align the panel so the loops are running in the opposite direction of the wood flooring material In wet areas such as bathrooms etc where a w...

Page 4: ...on in advance to be sure that you have the correct number of tracks when installing the tubing Transition and radius panels can be installed upside down as filler pieces When securing the panels to a wood subfloor we recommend using at least eight 8 countersunk screws spaced 12 30 cm apart and 6 15 cm from the edges When installing over concrete you can use countersunk concrete fasteners in the sa...

Page 5: ...utting the panel remove any burrs When cutting the last master panel in the first row use the rest of the panel to start the next row This will provide staggered joints for the field panels After completion of the panel installation in an area use a vacuum to clean up thoroughly before installing the tubing Dirt and debris in the tracks can create noise when the system is put into operation 5A 3 ...

Page 6: ...to fasten the tubes in the tracks Be sure to use a block when using a hammer or mallet to set the tubing to avoid denting the aluminum surface Follow the loop layout you have planned and connect the return tube to the manifold It is very important that the tubes are snapped down completely into the tracks When installing the tubing in the radius panels it is important to pull the tubing tightly ar...

Page 7: ...layment product in all ceramic tile installations Underlayment should be secured and seams finished per manufacturer s instructions It is also a good idea to use plasticizer additives with the mastic and grout for more flexibility during operation of the heating system Laminate Wood Flooring Thin laminate flooring may require the use of an underlayment material to provide additional support above ...

Page 8: ...o success are combinations of know how modern production sites and equipment latest production technologies and motivated personnel Roth Industries Inc 77 Circuit Drive North Kingstown RI 02852 Phone 401 267 9044 Fax 9048 http www Roth USA com E mail Roth USA Roth USA com Roth Canada 1607 rue de l Industrie Beloeil QC J3G 4S5 Phone 450 464 1329 Fax 7950 http www Roth Canada com E mail service roth...

Reviews: