Installation

 

1 - 

Observe if the gate is sliding freely in all its route, observing 

support guide, rail, stops and pulleys

  

2  - 

Provide a power and ground point, passing a conduit, 

starting from the 

driver to the power board 

with a 10A bipolar 

circuit breaker.

 

 

NOTE: It is mandatory to install a shutdown device (bipolar 

circuit breaker 

with minimum contact opening equal to 3mm

that must be incorporated into fixed wiring.  

3

 - 

Provide the means by which you want to fix the drive.

 

 

• Concrete Base • Metal Base • Cross Arm Brace (Air Base) Use 

the measurements in the manual to mark the location of the 

bolts.  

4- 

Place the washers on the base, screw the driver onto the 

washers and place the driver in the manual mode. 

5 - 

Close the gate, support the rack on the gear and fix the bar 

in the gate with solder or screw, 30 by 30 cm.

 

 

6 - 

Once the racks have been fixed, remove the washers placed 

on the base and fix the motor again, and check the spaces 

between the rack and the gear.

 

 

NOTE: 

" The washers placed at the beginning of the racks 

attachment serve to give the minimum mandatory height of 2 

mm between the rack and the external gear of the engine."

 

 

NOTE: 

" Failure to observe this distance may result in wear on the 

drive's internal and external gears or breakage of the rack with 

engine starting."

 

 

7- 

Adjust the end magnets in open mode 

FA 

and closed 

FF

placing a magnet on each end of the rack, observing the polarity of 

each magnet between open and closed gate.

 

 

NOTE: 

"The magnets must always be attached to the angle 

bracket, even during opening and closing adjustments to 

prevent damage to the control unit"

 

 

8  - 

Fix the control unit on the support guide inside the actuator 

(fixing instructions Page2).

 

9 - 

End of stroke 

HALL 

sensor The hall sensor identifies the 

polarity of the magnets, north and south. (instructions Page 6)

 

NOTE: For bench tests, it should simulate the movement of 

the magnet installed in the gate, remembering that when the 

control is activated the limit switch must be active.

 

In the installation and adjustment of the magnets, in the first 

two commands the control unit must recognize the FA and FF 

magnets.

 

10 - 

The use of the Active infrared sensor - SIA 30 is 

MANDATORY to activate the system of anti-locking protection, 

avoiding collision with obstacles, accidents with people or material 

goods.  

11 

- The gates and actuators need periodic maintenance and 

lubrication every 6 months for proper operation.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Rev 05/18 - COD. 12443 

www.rossiportoes.com.br 

Page 1

 

1

 

Support guide

 

Rail and Stopper

 

Pulleys

 

FA 

-End of stroke open gate

 

 

FF 

- End of stroke closed gate

 

 

2

 

3

 

4

 

Washers

 

Reviews: