Step 1
: Layout all Kabuki units on the floor below batten pipe or truss. Units with
trip mechanisms
indicated by
a plastic cover go on the ends with the plastic cover facing off-stage (If
trip mechanisms
are not installed, see
Trip Mechanism
instructions). Loosen
thumb screws
on all
pipe clamps
completely. You may also need to
loosen the
pipe clamp bracket nuts
slightly (just enough so they slide) using a 7/16” wrench.
Figure 2
Step 2
: Starting from the center of the batten pipe or truss, hang one Kabuki unit (aligned with center) and
tighten the
pipe clamp thumb screws
and
bracket bolts
.
Step 3
: Hang another Kabuki unit adjacent to the first and tighten the
pipe clamp thumb screws
only.
Pipe Clamp Thumb Screw