2-2
Start Up
Before Applying Power to the Drive
❏
1. Confirm that all inputs are connected to the correct terminals and are
secure.
❏
2. Verify that AC line power at the disconnect device is within the rated
value of the drive.
❏
3. Verify that control power voltage is correct.
The remainder of this procedure requires that a OIM be installed. If
an operator interface is not available, remote devices should be used
to start up the drive.
Important: When power is first applied, the OIM may require
approximately 5 seconds until commands are recognized
(including the Stop key).
Applying Power to the Drive
❏
4. Apply AC power and control voltages to the drive.
If any of the six digital inputs are configured to “Stop – CF”
(CF = Clear Fault) or “Enable,” verify that signals are present or the
drive will not start. Refer to
Alarm Descriptions on page 4-10
for a
list of potential digital input conflicts.
If a fault code appears, refer to
If the Ready LED is not flashing green at this point, refer to Status
Indicators and their indications below.
❏
5. Proceed to Running the Start-Up Routines.
Prepare For Drive Start-Up
Summary of Contents for 9VT201-007HTNNN
Page 1: ...VTAC 9 AC Drive Firmware Version 3 xx User Manual ...
Page 4: ...soc 2 ...
Page 14: ...P 8 Overview Publication 9VT UM001D EN P Notes ...
Page 56: ...1 42 Installation Wiring Publication 9VT UM001D EN P Notes ...
Page 62: ...2 6 Start Up Publication 9VT UM001D EN P Notes ...
Page 130: ...3 68 Programming and Parameters Publication 9VT UM001D EN P Notes ...
Page 150: ...4 20 Troubleshooting Publication 9VT UM001D EN P Notes ...
Page 176: ...A 26 Supplemental Drive Information Publication 9VT UM001D EN P Notes ...
Page 196: ...B 20 Using the LCD OIM Publication 9VT UM001D EN P Notes ...
Page 212: ...C 16 Application Notes Publication 9VT UM001D EN P Notes ...
Page 223: ......