9.3 Set-For-Flight
Step
Procedure
Date & Initials
Tech.
QA
9.3.1
Verify the DB-9 pin connector of the
SFF Power and Measurement Circuit
in
is visibly clean. Any debris could detrimentally contaminate the
Lightband’s mating socket connector.
9.3.2
Connect the Lightband to the
SFF Power and Measurement Circuit
per Figure
9-3. Do not apply power to the Lightband.
Figure 9-3: SFF circuit