5.
Handling Precautions
Lower Ring
1. Do not touch the ball screw. Be especially careful when installing fasteners adjacent the Motor Bracket
Assembly. See Figure 5-1.
2. Do not touch the portion of the Hinged Leaves that engage the Upper Ring. Do not wipe off the grease
during cleaning. See Figure 5-2.
3. Do not grab the motors or use them to rotate the Lower Ring.
4. Do not allow the motors to contact anything. This is especially crucial when rotating the Lower Ring. See
5. Do not touch the gear cover on the Motor Bracket Assembly. See Figure 5-4.
6. Do not grab the Separation Springs or use them to rotate the Lower Ring. See Figure 5-5.
7. Do not touch the Leaf Retaining Cord. This is especially applicable when attaching the Lower Ring to
adjoining structures. See Figure 5-6.
Upper Ring
1. Do not touch the Leaf groove. Do not remove grease from the groove when cleaning. See Figure 5-2.
2. Do not touch the spring plungers. Do not allow the spring plungers to contact anything. See Figure 5-7.
3.
Do not place the Upper Ring “face down” on a surface if there are Separation Connectors or Separation
Switches installed. Doing so could damage or contaminate Connector pins, Switch plungers or the Upper
Ring flange. See Figure 5-8
.
Figure 5-1: Carefully install fasteners immediately adjacent the MBA
Figure 5-2: Do not touch the Leaf lip or its corresponding groove in the Upper Ring