Replacing Components of the PPM Hydrogen Transmitter

This section includes procedures to replace the ppm hydrogen detector and amplifier.

Replacing the PPM Hydrogen Detector

1. Turn off power to the controller.

2. Place the controller’s on/off switch in the OFF position.
3. Remove the junction box cover.
4. Remove the detector terminal strip from its socket.
5. Disconnect the detector leads from the detector terminal strip. Note the position of the color-coded 

leads as you remove them.

6. Unscrew the detector from the junction box.
7. Guide the detector leads of the replacement detector through the bottom conduit hub of the 

junction box, then screw the mounting threads of the detector into the conduit hub.

8. Connect the detector leads to the detector terminal strip as shown in Table 3 below and Figure 4 on 

page 11 of this manual.

9. Re-install the detector terminal strip into its socket.

NOTE:

When a transmitter is first powered up with a new detector, its output may be high enough to 
cause an alarm or low enough to indicate a failure for a brief period before stabilizing within 
a few minutes. Be sure to make arrangements so that this does not cause unwanted alarms.

10. Turn on power to the controller.
11. Turn on the controller and place it into normal operation.
12. Allow the transmitter to run for 3 hours.
13. Perform a preliminary calibration as described on page 16. This will be a temporary calibration 

since the new ppm detector must burn-in before it can be properly calibrated.

14. Allow the replacement detector to burn-in for at least 5 days

 

before you continue with the next 

step. A burn-in period of 7 days is recommended.

15. After the burn-in period, calibrate the transmitter as described on page 16.

Table 3:Reconnecting the PPM Detector to the Amplifier

Detector Lead

Detector Terminal Strip

Red

R

White

W

Black

B

Summary of Contents for 65-2443

Page 1: ...RKI Instruments Inc www rkiinstruments com 65 2443 PPM Hydrogen Transmitter Operator s Manual Part Number 71 0542 Revision P1 Released 12 29 20...

Page 2: ...c calibration and maintenance of the detector is essential for proper operation and correct readings Please calibrate and maintain this detector regularly Frequency of calibration depends upon the typ...

Page 3: ...air costs transportation costs or contingent expenses incurred without our prior approval THIS WARRANTY IS EXPRESSLY IN LIEU OF ANY AND ALL OTHER WARRANTIES AND REPRESENTATIONS EXPRESSED OR IMPLIED AN...

Page 4: ...up 12 Introducing Incoming Power 12 Transmitter Burn In Period 12 Setting the Zero Signal 12 Maintenance 13 Preventive Maintenance 13 Troubleshooting 13 Replacing Components of the PPM Hydrogen Transm...

Page 5: ...en transmitter WARNING When using the 65 2443 you must follow the instructions and warnings in this manual to assure proper and safe operation of the 65 2443 and to minimize the risk of personal injur...

Page 6: ...hydrogen transmitter s components It is a 4 to 20 mA type detector head It consists of the ppm hydrogen detector amplifier and junction box Figure 1 Component Location Amplifier J Box Hydrogen Detecto...

Page 7: ...lifier see below Amplifier The amplifier converts the non linear electrical output from the detector to a linear 4 to 20 mA signal that corresponds to the detection range and transmits the signal to a...

Page 8: ...side of the amplifier see Figure 2 The test points produce a 100 to 500 mV output that corresponds to the transmitter s 4 to 20 mA output Use the test points and a voltmeter to measure the amplifier...

Page 9: ...the mounting site Select a site where the transmitter is not likely to be bumped or disturbed Make sure there is sufficient room to perform start up maintenance and calibration procedures Select a sit...

Page 10: ...rough the top conduit hub of the junction box 7 Pull out the controller terminal strip and connect the three wires to the terminal strip as follows see Figure 4 Connect the positive wire to the PWR SI...

Page 11: ...rogen Transmitter to a Controller 12 If shielded cable is used connect the cable s drain wire to an available chassis earth ground at the controller RKI controllers typically have a ground stud that c...

Page 12: ...on the controller 5 Verify that the controller is on and operating properly Refer to the controller operator s manual Transmitter Burn In Period Once power has been applied to the transmitter it will...

Page 13: ...obable Causes Recommended Action Fail Condition Controller indicates a fail condition The transmitter wiring is disconnected or misconnected The transmitter is malfunctioning 1 Verify that the transmi...

Page 14: ...Figure 4 on page 11 of this manual 9 Re install the detector terminal strip into its socket NOTE When a transmitter is first powered up with a new detector its output may be high enough to cause an al...

Page 15: ...Figure 4 on page 11 of this manual If controller leads or detector leads were removed during this procedure refer to Tables 4 and 5 below 8 Install the amplifier into the junction box with the screw l...

Page 16: ...or the environment is not well controlled then more frequent calibration than every 6 months may be necessary Calibration This section describes how to calibrate the ppm hydrogen transmitter It includ...

Page 17: ...rogram or disable external alarms before continuing Setting the Zero Reading The detector s zero setting is controlled by electronics and is not user adjustable Setting the Span Reading 1 Screw the re...

Page 18: ...transmitter includes detector and amplifier 71 0542 65 2443 PPM Hydrogen Transmitter Operator s Manual this document 81 0000RK 01 Calibration cylinder 1 000 ppm hydrogen in air 34 liter steel 81 0000R...

Reviews: