5. Any compound used on the threaded joint of gas piping shall be a type which resists the action of
liquefied petroleum gas.
6. Supplied gas pressure must be within the limits shown in the specifications.
7. After completion of gas pipe connections, all joints including the heater must be checked for gas-
tightness by means of leak detector solution, soap and water, or an equivalent nonflammable
solution, as applicable.
CAUTION:
Since some leak test solutions, including soap and water, may cause
corrosion or stress cracking, the piping shall be rinsed with water after testing, unless
it has been determined that the leak test solution is noncorrosive.
8. The appliance and its appliance main gas valve must be disconnected from the gas supply piping
system during any pressure testing of that system at test pressures in excess of 1/2 psi (3.5kPa).
The appliance must be isolated from the gas supply piping system by closing its equipment shut-off
valve during any pressure testing of the gas supply piping system at test pressures equal to or less
than 1/2 psi (3.5kPa).
9. A valve supplied must be installed on back of unit at time of installation. This is for compliance to
ANSI standard Z21.11.2. Valve is packaged with unit.
MANUAL VALVE
10. After completing pipework, secure the heater to the floor.
Use the two screws provided,as shown in the drawing.
To prevent deforming floor fixing plate ,do not over torque screws.
- 8 -
OPEN
CLOSED
2 SCREWS
Summary of Contents for RCE-592ACPA
Page 24: ... 22 ...
Page 25: ... 23 ...
Page 26: ... 24 ...
Page 27: ... 25 ...
Page 28: ... 26 ...
Page 31: ... 29 ...