HD250i Combination Flueing Installation: 0-08

General Information

Before Installation

Existing Flue or 

Chimney

Ensure HD250i Can 

Be Easily Removed

Other Supplier Flue 

Components Can 

Not Be Substituted

Clearance for 

Exhaust Flue 

Components

Flue Must Be 

Supported

Flue Terminal 

Clearances

Connecting Flue 

Components

Maximum Flue 

Length and 

Number of 90° 

Bends

Not to be Confused 

with Direct Flueing

Inspect each flue component for damage. Do not attempt to fix or install 

any damaged components.

Do not connect with any existing flue or chimney. Do not common flue 

with the flue pipe of any other water heater or appliance.

For servicing, repair or replacement, ensure the Rinnai HD250i can 

be removed without causing damage to the installation. This can be 

achieved by using an adjustable flue component (FFHD250PIPEADJ) as 

the first section on top of the appliance.

The Rinnai HD250i is a direct flue water heater and is only certified 

and listed with Rinnai flue components (excluding air inlet and 

protective mesh). Do not combine or use flue components from other 

manufacturers. Only the flue components identified in this installation 

manual are to be used for horizontal, vertical and combination flueing.

The exhaust flue components are single skin and need to maintain a 

25mm clearance from combustibles as per NZS 526:2003 2.6.2..

Flue must be supported and be independent of the appliance.

Ensure positioning of the flue terminal and flue installation comply 

with NZS 5261:2003, ‘Table 16 - Minimum clearances required for flue 

terminals shown in figure 3’.

Flue connections must be firmly pressed together so that the gaskets 

form an air tight seal. 

Number 

of 90° 

Bends

Maximum 

Flue 

Length

Dip Switch Setting*

0

2.5m

If the length is < 6.5m then move the dip switch no. (SW) to ON

0.5m

If the length is < 5.0m then move the dip switch no. (SW) to ON

2

8.5m

If the length is < 3.0m then move the dip switch no. (SW) to ON

3

7.0m

-

4

5.0m

-

5

3.5m

-

6

.5m

-

* Duct resistance varies with flue length so dip switch settings need to be adjusted to 

 

   vary the fan speed.

Components for this Rinnai flueing application cannot be interchanged 

with the Rinnai Direct Flueing solution. Direct flueing is for installations 

where the HD250 Internal is mounted directly on the inside of an 

external wall (cannot be extended).

Summary of Contents for Efficiency HD250i

Page 1: ...ing Installation Manual This appliance shall be installed in accordance with Manufacturer s Installation Instructions Local Gas Fitting Regulations NZS 5261 Installation Code Municipal Building Codes...

Page 2: ...and fully check the operation of the water heater before leaving site including the temperature of the water delivered WARNING Improper installation adjustment alteration service or maintenance can c...

Page 3: ...ue components from other manufacturers Only the flue components identified in this installation manual are to be used for horizontal vertical and combination flueing The exhaust flue components are si...

Page 4: ...Exhaust Exhaust Intake Relationship Condensate Each requires a 90 bend to prevent entry of rain Intake must be located in relation to the exhaust as shown below Horizontal flues must slop 20mm per met...

Page 5: ...ensate drain and trap as close as possible to the appliance Condensate drain trap must contain a minimum of 75mm 500mm clearance shown is for simple roof pitches Complex multiple pitched roofing can i...

Page 6: ...ion Predrill two small holes at the end of the air intake pipe Slide the pipe over the air intake terminal 2 With self tapping screws attach the pipe to the air intake terminal 3 Apply a bead of silic...

Page 7: ...tainless steel 300mm stainless steel pipe can not be cut to size FFHD250PIPE900 HD250i Flue Pipe 900mm Stainless steel 900mm stainless steel pipe can not be cut to size FFHD250PIPEADJ HD250i Flue Adju...

Page 8: ...Installers 0800 TO RINNAI 0800 86 746 624 Rinnai New Zealand Limited 105 Pavilion Drive Airport Oaks PO Box 53177 Mangere Auckland Airport Manukau Manukau 2150 Phone 09 257 3800 Fax 09 257 3899 Email...

Reviews: