5.7
Securing the burner to the boiler
Divide the combustion head from the rest of the burner, as shown
in Fig. 14; you have to:
loosen the 4 screws 3) and remove the cover 1);
remove screws 2) from the two slide bars 5);
disconnect plug 14), unscrew cable grommet 15);
disconnect the socket of the maximum gas pressure switch;
remove the 2 screws 4);
draw the burner back on the slide bars 5) by about 100 mm;
disconnect the probe and electrode cables, then completely
unthread the burner from the slide bars.
As soon as this operation is completed (if necessary):
fix the flange 9) to the plate of the boiler interposing the
insulating flange gasket 8) supplied with the unit.
Use the 4 screws supplied, with a tightening torque of 35 -
40 Nm, after protecting their thread with anti-seizing
products.
5.8
Combustion head adjustment
At this point of the installation, the combustion head is fixed to the
boiler as shown in Fig. 12. It is therefore especially easy to adjust,
and this adjustment depends only on the maximum output of the
burner.
Two combustion head adjustments are available:
–
external air R1
–
central gas/air R2
In the diagram of (Fig. 15), find the notch at which both air and
central gas/air should be adjusted.
Provide an adequate lifting system of the burner.
ATTENTION
The burner-boiler seal must be hermetic; after
burner start-up check there is no leakage of flue
gases into the external environment.
Fig. 14
20057405
Fig. 15
D1718
No. notches
Max burner output
Summary of Contents for RS 160/M BLU
Page 2: ...Translation of the original instructions...