Installation
5.8
Combustion head adjustment
At this point of the installation, the combustion head is fixed to the
boiler as shown in Fig. 15.
It is therefore especially easy to adjust, and this adjustment de-
pends only on the maximum output of the burner.
Two adjustments of the head are foreseen:
–
external air R1
–
central air R2
In the diagram (Fig. 20) find the notch at which to adjust both air
and central air.
External air R2 adjustment
Rotate the screw 4)(Fig. 18 - Fig. 19) until the notch you
have found corresponds with the front surface 5) of the fit-
ting.
Central air R3 adjustment
Loosen the 2 screws 1) and rotate the ring nut 2) until the
notch you have found corresponds with the screw 1).
Block the 2 screws 1).
WARNING
To facilitate adjustment, loosen the screw 6),
adjust and then lock.
2
(R2)
1
3
6
4
(R1)
5
D7675
Fig. 18
Fig. 19
0
1
2
3
5
4
6
(R1)
1
2
(R3)
3
20127192
Summary of Contents for RS 160/E O2 BLU
Page 2: ...Translation of the original instructions...
Page 45: ...43 20164541 GB Appendix Electrical panel layout...
Page 47: ...45 20164541 GB Appendix Electrical panel layout...
Page 48: ...20164541 46 GB Appendix Electrical panel layout...
Page 49: ...47 20164541 GB Appendix Electrical panel layout...
Page 57: ......
Page 58: ......
Page 59: ......