2.3

Unpacking

Remove all packing material and inspect the scale for damage possibly caused during shipment. Contact Rice Lake 
Weighing Systems and the shipper immediately if there is damage to the scale.

All 

RoughDeck PW-1

 models have eye bolts in the end of the deck for use when lifting the scale with chains and a 

spreader bar.

Lift the scale only with a properly designed spreader bar as shown in Figure 2-1.

Lifting force must be vertical to avoid bending the eye bolts.

Figure 2-1. Proper Lifting Technique

2.4

Assembly

The following sections describe the assembly of the components of the 

RoughDeck PW-1

 scale.

2.4.1

Adjusting Feet

The scale feet are shipped detached from the load cells for load cell protection during shipping. The feet are 
secured to the shipping pallet along with the load cell cable and product literature. 

1. Unpack all parts.

2. Ensure each foot is screwed in until the foot touches either the load cell or the underside of the deck; then, 

unscrew each foot three complete turns.

3. Place a spirit level on the deck. 

4. Adjust corners not contacting the floor by unscrewing the feet on those corners until they just contact the 

floor surface. 

5. When all the feet are in contact with the floor, check the deck with the spirit level to ensure the scale is 

within 1/4'' of level.

2.4.2

Mounting Plate Installation

The scale should be secured to the floor to prevent sideways movement for permanent applications. Two optional 
mounting plates, with holes slightly exceeding the foot diameter, are available for that purpose.

1. Lift the scale until the feet are approximately 1'' off the floor. 

2. Slide the mounting plates under two diagonally opposed feet. 

3. Lower the scale back to the floor and position the plates as shown in Figure 2-2 with the boltdown holes 

Important

Summary of Contents for RoughDeck PW-1

Page 1: ...RoughDeck PW 1 Low Profile Floor Scale Installation Manual PN 179344...

Page 2: ...marks of their respective companies All information contained within this publication is to the best of our knowledge complete and accurate at the time of publication Rice Lake Weighing Systems reserv...

Page 3: ...intenance 8 4 3 Load Cell Replacement 8 4 3 1 Remove Load Cell 8 4 3 2 Install Load Cell 8 4 3 3 Load Cell Wiring to the Junction Box 9 4 3 4 Replacement Parts List and Accessories 10 RoughDeck Limite...

Page 4: ...ii RoughDeck PW 1 Installation Manual Rice Lake continually offers web based video training on a growing selection of product related topics at no cost Visit www ricelake com webinars...

Page 5: ...s that are exposed when guards are removed WARNING Indicates a potentially hazardous situation that if not avoided could result in serious injury or death Includes hazards that are exposed when guards...

Page 6: ...ted to an earth ground with a ground interface cable of no more than 3 resistance throughout its length Load Cell Excitation Rated Excitation 10 VDC Maximum Excitation 15 VDC Grade Level Requirements...

Page 7: ...age could occur from side impacts of wheels or forklift tines Avoid areas where falling objects could cause shock damage Avoid areas where water may damage a scale not meant for a washdown environment...

Page 8: ...pallet along with the load cell cable and product literature 1 Unpack all parts 2 Ensure each foot is screwed in until the foot touches either the load cell or the underside of the deck then unscrew e...

Page 9: ...receptacle connector is on the short cable coming from the junction box at the top end of the scale To connect the two cables 1 Plug the pin end from the indicator cable into the receptacle end of the...

Page 10: ...is not necessary A test weight of 25 of scale capacity recommended for this procedure Example 500 lbs for 2000 lb models 5000 lbs for 20 000 lb models 1 Remove the junction box cover and identify the...

Page 11: ...oad the scale to near capacity two or three times 2 With no load on the scale place the indicator in calibration mode and perform a zero calibration 3 Place test weights on the platform equal to 70 80...

Page 12: ...box as viewed from the bottom To verify correct load cell junction box terminal matching see the numbers on the terminals inside the junction box and the corner numbering diagram in Figure 4 2 Issue...

Page 13: ...et in the junction box cover or through cable fittings in the NEMA Type 4X junction box 9 Corner correction trimming and calibration is necessary after load cell replacement Follow the instructions in...

Page 14: ...Stainless Steel Nema 4X 1 6 14932 Screw Cap 10 32NF X 3 8 Hex Socket Button Head Alloy Steel Black Oxide 4 7 178613 Eyebolt 5 16 18NC X 1 1 8 Shank 900 lb Steel Zinc Plated 2 8 14664 1 2 20 NF Jam Nu...

Page 15: ...4 Optional Wheel Assembly Table 4 3 Wheel Assembly Parts List Item No Part No DESCRIPTION QTY 1 178240 Bracket Wheel 1 2 178178 Wheel 1 3 25511 Screw Cap 5 16 18NCX1 3 4 Hex Head SST 1 4 35170 Nut Lo...

Page 16: ...RLWS confirms that the nonconformity actually exists and was not caused by accident misuse neglect alteration improper installation improper repair or improper testing RLWS shall be the sole judge of...

Page 17: ......

Page 18: ...54868 USA U S 800 472 6703 Canada Mexico 800 321 6703 International 715 234 9171 Europe 31 0 26 472 1319 Rice Lake Weighing Systems is an ISO 9001 registered company Rice Lake Weighing Systems Speci c...

Reviews: