Page 1: ...RoughDeck CS Rail Car Coil Scale Installation Manual April 16 2021 PN 206036 Rev A...

Page 2: ...marks of their respective companies All information contained within this publication is to the best of our knowledge complete and accurate at the time of publication Rice Lake Weighing Systems reserv...

Page 3: ...d asking for the training department 1 0 Introduction 1 1 1 Safety 1 1 2 Scale Components 2 2 0 Installation 3 2 1 Recommended Equipment and Tools 3 2 2 Lifting and Handling 3 2 3 Temporary Setting Bl...

Page 4: ...k CS Rail Car Coil Scale ii Visit our website www RiceLake com Rice Lake continually offers web based video training on a growing selection of product related topics at no cost Visit www ricelake com...

Page 5: ...en guards are removed Indicates a potentially hazardous situation that if not avoided could result in minor or moderate injury Indicates information about procedures that if not observed could result...

Page 6: ...ake com 1 2 Scale Components The RoughDeck CS Rail Car Coil Scale has major components including Assembled weighbridge module Weighbridge fasteners Load cells Load cell mounts with leveling bolts and...

Page 7: ...each corner of the scale Torque wrench to 100 ft lb Socket wrenches to 1 1 2 drive compatible with torque wrench Box end wrenches to 1 1 4 Open end wrench set 7 16 and 1 1 4 4 bubble level Small torp...

Page 8: ...connecting of the deck module Use leveling bolts in the base plate to level the scale Setting blocks are only used in the corners of the module where the load cell mounts are installed When placing m...

Page 9: ...ount blocks ground straps and anchor bolts 3 1 Baseplate and Load Cell Installation Use the following steps for installing the mount baseplate and load cell in the load cell mount pockets 1 Remove the...

Page 10: ...g or misalignment 12 Use an individual hammer drill to drill a 3 4 hole into the concrete at least 6 deep on one side of the mount frame 13 Drill a second anchor bolt hole on the opposite side of the...

Page 11: ...n Figure 4 1 Load Cell Pocket Numbering 3 Wire each load cell to the junction box terminal strip in accordance with the wiring code contained in the Certificate of Conformance CC Load cell pockets are...

Page 12: ...e guide shown in Table 4 1 and the labels on the terminal strips of the junction box To verify the wiring scheme see the Certificate of Conformity CC shipped with each load cell 8 For performance use...

Page 13: ...nections in the junction box Pull the load cell cable out of the conduit Attach a pull cord to the load cell cable at the junction box before pulling the cable through the conduit 4 Remove the two loa...

Page 14: ...that restrict movement 4 If check rods are used loosen all connections to finger tightening only for testing 5 Check load cell cables for physical or water damage If after all these checks the proble...

Page 15: ...ent available from RLWS Equipment Return Department Examination of such equipment by RLWS confirms that the nonconformity actually exists and was not caused by accident misuse neglect alteration impro...

Page 16: ...RoughDeck CS Rail Car Coil Scale 12 Visit our website www RiceLake com...