89
Field Selections
FIELD SELECTIONS & ADJUSTMENTS
FIELD SELECTIONS –– DIPSWITCHES
A dipswitch bank; SW1 is provided for some field adjust-
ments. Heating blower off delay, cooling (and heat-pump)
blower off delay, display (7-Segment) orientation and fault
clear are the adjustments and functions that can be han-
dled using the dipswitches.
Seven-Segment Display Orientation; SW1
As the control will be applied in a multi-position furnace a
means of changing the orientation of the seven segment
display is required. This dipswitch is to be labeled SW1.
Factory setting of the SW1 dipswitch is OFF. The factory
setting display orientation is with the control placed in a
vertical orientation and the low voltage terminal block T2 is
in the bottom position.
Heat Blower-Off Delay; SW2 & SW3
A means of controlling the HEAT speed blower “off” delay
time is provided. The dipswitches are labeled SW2 and
SW3. The following table defines the settings:
SW2
SW3
OFF
OFF
90 seconds
(Factory Setting)
ON
OFF
120 seconds
OFF
ON
160 seconds
ON
ON
180 seconds
Cooling & Heat-Pump Heat Blower Off Delay; SW4
A means of controlling the COOL speed blower “off” delay
time is required. The dipswitch is labeled SW4. The follow-
ing table defines the settings:
SW4
OFF
30 seconds (Factory Setting)
ON
45 seconds
FIGURE 47
DIPSWITCH MAP
ST-A1210-03
Summary of Contents for 95MSP series
Page 34: ...34 Field Conversions ...
Page 35: ...35 Field Conversions ...
Page 36: ...36 Field Conversions ...
Page 37: ...37 Field Conversions ...
Page 38: ...Field Conversions 38 ...
Page 99: ...99 ...
Page 100: ...100 CM 0716 ...