LOCATION OF FLUE TERMINAL FOR POWER FLUE

Listed below are the minimum clearances required for fan-assisted terminations:
1.

Below eaves, balconies and other projections. .........................................................200mm

1a. Below eaves, balconies and other projections for a 1500 & 1800 model..................300mm
2.

From the ground, above a balcony or other surface..................................................300mm

3.

From a return wall or external corner.........................................................................300mm

4.

From a Gas meter....................................................................................................1000mm 

5.

From an electricity meter or fuse box. .......................................................................500mm

6.

From a drainpipe or soil pipe.......................................................................................75mm 

7.

Horizontally from any building structure or obstruction facing a terminal. .................500mm

8.

From any other flue terminal. Cowl, or combustion air intake. ..................................300mm

9.

Horizontally from any openable window, door, non-mechanical air inlet, 

or any other opening into a building with the exception of sub floor ventilation.........300mm

10. From a mechanical air inlet including a spa blower.................................................1000mm
11.

Vertically below an openable window, non-mechanical air inlet, 

or any other opening into a building with the exception sub floor ventilation.............500mm

ELECTRICAL

SHOULD THE SUPPLY FLEX AT THE BACK OF THE FIREBOX BE DAMAGED, A SPECIALLY

PREPARED FLEX IS REQUIRED. FOR REPLACEMENT CONTACT THE MANUFACTURER.
THE ON/OFF WALL SWITCH MUST NEVER BE ATTACHED TO A METAL FRAME.

WARNING

Whenever servicing the power flue system, always turn off the electrical power supply and

close the manual gas control valve.

IMPORTANT INFORMATION

In addition to the instructions in this manual all national, state and local regulations must be

adhered to. These include but are not limited to:
• Australian Standards AS3000 - Electrical Installation.
• Australian Standards AS/NZS5601.1-2013 - Gas Installation.
• Local Gas and Electrical Authority Regulations.
• Municipal Building Codes.
The power flue should be serviced every 12 months by an authorised technician. If repairs

are needed an authorised technician must carry them out.

FITTING THE MOTOR

The Power Flue motor is fitted with two sets of spigots. The set on the base of the Power Flue box

sit on top of the vertical flue and the set mounted on the side plate connect to the horizontal flue.

6

Summary of Contents for Power Flue

Page 1: ...POWER FLUE INSTALLATION OPERATING MANUAL The Real Flame Power Flue system is approved to be installed with any open fronted Real Flame gas fireplace VERSION 16...

Page 2: ...en installed in an outdoor setting 4 Limit of Liability The warranty provided under this warranty is limited to replacement or repair of the Real Flame Gas Burner only at our option To the extent perm...

Page 3: ...d any other relevant statutory regulations IMPORTANT NOTES The Real Flame power flue system is designed and manufactured by Real Flame and is approved to be installed with the following Real Flame Pro...

Page 4: ...Clearance 10 Frameout 11 Motor exploded view 12 Dimensions 13 Internal Motor 15 External Motor 15 Troubleshooting Electronic Ignition and Power Flue System 16 Wiring Diagram 18 Parts List 18 Interfac...

Page 5: ...OWER FLUE MOTOR Access must be provided to the flue motor this access MUST be at least 400mm x 400mm There MUST be a minimum clearance of 250mm between the top of the motor and any fixed object i e ce...

Page 6: ...other opening into a building with the exception sub floor ventilation 500mm ELECTRICAL SHOULD THE SUPPLY FLEX AT THE BACK OF THE FIREBOX BE DAMAGED A SPECIALLY PREPARED FLEX IS REQUIRED FOR REPLACEME...

Page 7: ...which the motor fits to or the 150 200 twin skin flue if required The flow arrow on the muffler is to be pointing up If a 1800 or 3300 unit is used the flue is 200mm 250mm WIRING see wiring diagram p...

Page 8: ...een 4 and 8 may be used These values will give flue gas temperatures of 140 C and 220 C respectively For appliances with modulating burners the CO2 concentration in the flue shall be considered when t...

Page 9: ...dule Kit Standard Power Lead Wall switch for On Off Kit Electronic Ignition Kit Baffled Flue Kit Z C Heatseeker Series Powered flue kit comprising Indicated on Diagram as Kit 1 x Fan motor 1 x Control...

Page 10: ...Minimum clearance 250mm 150mm 200mm twin skin flue optional for additional height Ensure there is adequate ventilation within this cavity to prevent motor over heating Baffle Height 980mm and diamete...

Page 11: ...TYPICAL POWER FLUE FRAMEOUT 11...

Page 12: ...POWER FLUE MOTOR Fan Casing Pressure Differential Switch Motor 12...

Page 13: ...D E F G H 302 348 345 55 5 90 40 20 200 250 150 200 I J K L M N O P 13 20 120 60 105 75 45 112 MODELS H mm G mm Double Vision Hot Box and all Heatseekers 150 200 Pure Vision Simplicity Elegance Signat...

Page 14: ...DIMENSIONS Internal Power Flue Motor Internal Power Flue Motor 200 250 A B C D E F G H 268 281 331 311 202 152 300 128 A B C D E F G H 268 281 322 336 252 202 336 128 14...

Page 15: ...on 250mm min 900mm Min Distance Domestic 220mm 200mm or 300mm 500mm 25mm Flush Cowl termination Top Termination Flue Access Panel EXTERNAL MOTOR Baffle Heater 150mm x 200mm twin skin flue if required...

Page 16: ...ront of burner B The power polarity is reversed Check polarity B Sparker is to far from metal C Pressure switch Power Flue is not operating correctly Adjust sparker so it cross lights to metal Remove...

Page 17: ...red LED light that indicates the possible cause of a problem the LED light will flash in different sequences for different problems the most common are Long Flash Short Flash 1 0 Normal Running State...

Page 18: ...ING DIAGRAM LED Indicator TECHRITE POWER FLUE CONTROL MODULE Heat Sensor Sparker Power Fan Pressure Switch Double Block Solenoid NOTE For C Bus and or make up air damper interlock systems refer to pag...

Page 19: ...s required by the manufacturer see installation manual The damper is to operate from 240V power The damper must have an interlock signal that activates in the fully open position The make up air dampe...

Page 20: ...en allow the gas to the fire and the fire will ignite After operating for 60 seconds the module will check that the make up air damper interlock safety switch is in the closed position which indicates...

Page 21: ...21...

Page 22: ...22...

Page 23: ...23...

Page 24: ...elong hotmail com au Sydney NSW Showroom 546 Pacific Highway Chatswood NSW 2067 Ph 02 8905 0189 Fax 02 8905 0192 E mail info realflame com au Miranda NSW Showroom 36 Kareena Rd Miranda NSW 2228 Ph 02...

Reviews: