Installation: 

 
1.  Screw the studded rod (E) into the base of the tap (A). 

 

2.  Screw the hot and cold tail pipes (D&I) into the base of the tap, note: the drawing identifies the water inlets. 

 

3.  Pass the base plinth (B) and then upper seal (C) over the studded rod (E) and tail pipes (D&I) and locate them centrally on the 

base of the mixertap (A). 

 

4.  Place the mixertap (A) onto the sink or worktop and pass the tail pipes (D&I) and studded rod (E) through the taphole. With the tap 

in place check that the tail pipes (D&I) meet the hot and cold water feeds. If further adjustment to the plumbing is required do this 
now. Note: the tail pipes can be carefully bent to allow more space for the plumbing fittings. 

 

5.  Pass the rubber horseshoe (F) and then metal horseshoe (G) over the studded rod (E) and around tail pipes (D&I). 

 

6.  Fasten the fixing nut (H) securely onto the fixing stud (E) fixing the tap into its correct location. 

 

7.  Connect the hot tail pipe (D) to the water supply using ½” BSP x 15mm compression fittings or similar. 

 

8.  Connect the cold tail pipe (I) to the water supply using ½” BSP x 15mm compression fittings or similar. 

 

 

 

Key: 

Description: 

Qty. 

 

Tap body 

 

Base plinth 

 

Upper seal 

 

Hot copper tail pipe 

 

Fixing stud 

 

Rubber horseshoe 

 

Metal horseshoe 

 

Fixing nut 

 

Cold copper tail pipe 

 

 
After installation: 

 

Once you have visually checked the installation of the new 
tap and all connections, ensure that all other fittings are 
closed except the new tap which should be left open.  
 
Turn on your water heating system and ensure that your 
mains stopcock is open. Reconnect both the hot and cold 
water supplies to this fitting. 
 
Check the function of flow and function of hot, cold and 
mixed water. 
 
Turn off the tap and check carefully for any leaks around all 
connections on the fitting and adjoining plumbing. 
If possible return to the installation after a longer period to 
double check for slower leaks. If pressure testing 
equipment is available check the installation to the 
maximum recommended pressure. 
 
Clean the tap to remove any marks created during 
installation as instructed then place a bag over the product 
to protect the tap until it is ready for use. 
 
The installation should be periodically checked for damage, 
if the property is left unattended for a prolonged period we 
recommend isolating water supplies. 
 

 

 

 

 

Reviews: