Piping, ventilation
The outgoing pipe of the property's BDT pipeline is connected to the incoming
connection of BioBox M (D75 mm).
If the diameter of the property's sewer pipe is 110 mm, an extension piece is
used. Outgoing pipe from BioBox M is connected to the outgoing connection
(D75 mm) and it is connected to the pipeline (D75 (or
D100; needed extension piece)) which is led into a ditch via a sampling well
or filtered inside the soil with an infiltration well (if possibility of sampling is
needed).
If there is pipeline ventilation to the roof (1) BioBox M is ventilated to the roof.
If not, BioBox M has a ventilation connection between the house and the
device (2).
Also incoming air to BioBox M system is needed from the end of the pipeline
(open ditch) or from the infiltration to the ground (3).