1. INSTALLATION
INST
ALLER
1.1.7. POSITIONING AND CLEARANCES TO COMBUSTIBLE MATERIAL AND
SERVICE CLEARANCES
The boiler must be installed only on a vertical
solid wall, able to sustain its weight.
This boiler has been certified to be installed with
“0” clearances to combustible material.
In order to allow the access inside the boiler for
maintenance operations, follow the minimum
service clearances indicated in figure 5.
To facilitate the installation, the boiler is provided
with a jig that allows setting in advance the
connections to the tubes providing the ablility
of connecting the water heaters to completed
masonry structure.
1.1.8. ATTACHING THE BOILER TO WALL
To position the unit, proceed as follows:
1. Trace a line using a spirit level (min. length 25 cm / 10”) on the installation wall (fig. A).
2. Mark the two points to insert the two screws (fig. B) and drill the wall (fig. C).
3. Fix the wall bracket using the screws (fig. D) provided. Hang the boiler using the attached holes (E-F).
H
B
A
Y
X
15.98"
(406mm)
15.98"
(406mm)
HOLES
FIXING
INSTALLATION
A - 7.8 inch
B - 11.8 inch
X - 0 inch
Y - 0 inch
H - 20 inch
fig. 5
fig. F
fig. A
fig. B
fig. C
fig. D
fig. E