WP1FC FULL CUT-OFF INSTALLATION INSTRUCTIONS
Thank you for buying RAB Lighting fixtures. Our goal is to design the best quality products to get the job done right.
We’d like to hear your comments. Call the Marketing Department at 888-RAB-1000, or email: [email protected]
IMPORTANT
READ CAREFULLY BEFORE INSTALLING FIXTURE. RETAIN INSTRUCTIONS FOR FUTURE REFERENCE.
RAB fixtures must be wired in accordance with the National Electrical Code and applicable local codes. Proper grounding
is required for safety. Wallpacks are for outdoor use and should not be used in areas with limited ventilation or
high-ambient temperatures. Installation should be done by a qualified electrician.
WARNING: Make certain power is OFF before installing or maintaining fixture.
MOUNTING
Use the
Drilling Template
on the inside back
surface of the housing to match most standard junction
boxes or for more secure installation, lag bolt housing to
mounting surface using locations shown below.
1. Swing open door by loosening two screws.
Remove reflector and lift door off hinges.
2. Prepare the housing for use by knocking out the ap-
propriate holes.
3. Line up the housing in desired location and mount
securely.
4. Complete the wiring to the supply wires and ground
(see wiring instructions).
5. Replace the reflector, install the lamp slide door onto
hinges. Swing door close and tighten two screws.
6. To insure weatherproof seal make sure all holes
(mounting, plugs, conduit, etc.) are sealed with
weatherproof silicone sealant.
LOCATION
Mount fixture on a wall with lens facing down as shown
above. Fixture must be level. Lamp must be in a horizon-
tal position. DO NOT mount in a way that would entrap
heat.
WIRING
HID ONLY CAUTION:
125
°C supply wire required - Not
for use in dwellings.
To use 90°C supply wire, use
additionally supplied 12” leads and make supply
connections inside the junction box
.
All QT units are factory wired for 120V except those
factory ordered with a 277V Photocell (/PC2). If other
voltages are required, remove reflector and rewire for the
appropriate voltage. Do not use any supply voltage other
than those specified below.
WP1FCSN35-150
HPS
120V only
WP1FCSH50-150QT
HPS 120,208,240,277V
WP1FCH50-100QT, 125PSQ MH
120,208,240,277V
WP1FC26,32,42
CFL
120V thru 277V*
*No internal wiring changes needed for various voltages
as the ballast is quad tap electronic.
1. Connect the appropriate voltage fixture lead to the HOT
supply lead.
2. Connect the “COM” fixture lead to the COMMON supply
lead.
3. Fixture ground screw must be connected to supply
ground.
4. All unused leads must be capped and insulated.
Drilling Template
Lag Bolt Locations