Quadra-Fire • HUDBAY-INS • 7008-115 Rev. o • 8/11
28
11
11
Finishing
A. Mantel and Wall Projections
WARNING! Risk of Fire! Comply with all minimum clear-
ances to combustibles as specifi ed. Framing or fi nishing
material closer than the minimums listed must be construct-
ed entirely of noncombustible materials (i.e., steel studs,
concrete board, etc).
Clearance to combustible material under the insert is 3/8
inch (10 mm). Clearance from sides of fi replace opening
to combustibles is 12 inches (305 mm). Clearance from
top of fi replace opening for combustibles extending 1 inch
to 8 inches max. is 14 inches.
• Use leveling legs to raise insert minimum 3/8inch (10
mm) above combustible material or outer wrap of factory
built fi rebox.
Combustible facings must not extend behind the insert
surround.
Figure 11.1 Clearance to Combustibles
Model
A
B
C
D
Hudson Bay Insert
Inches 14
11
12
7
Millimeters
356
279
305
178
Underneath bottom of appliance to combustibles: 3/8 in. (10 mm)
16 in. (406 mm) front floor protection required 0 in. to 2-1/2 in. (64 mm) below bottom of appliance. (1/2 in. of "k" = .84)
No floor protection needed if 2-1/2 in. (64 mm) or greater from bottom of appliance.
To 8 in. (203 mm ) Deep mantel:
14 in. (356 mm) From top of insert
A
B
D
C
SIDE WALL
HEARTH
1-1/2 in. (38 mm)
16 in. (406 mm)