![background image](http://html1.mh-extra.com/html/qc-industries/pf26-conveyors/pf26-conveyors_installation-operation-and-maintenance-instructions-manual_3117431005.webp)
PF Conveyors | Installation, Operation & Maintenance Instructions
5
u
Connect control panels (continued)
/
Verbindung der Steuergeräte (Fortsetzung)
Weekly Cleaning / Nettoyage de la semaine / Wöchentliche Reinigung
qcconveyors.com
6
5
4
3
2
1
10
9
8
7
Daily Cleaning / Nettoyage du jour / Tägliche Reinigung
qcconveyors.com
9
8
7
6
5
4
3
2
1
3x
EN
9
Affix daily and weekly cleaning
instructions in a prominent
place
10
Repeat this procedure
for the second conveyor.
DE
Répéter la procédure pour le
second convoyeur
Wiederholen Sie diese Schritte für
das zweite Förderband.
u
Test Control Panel
/ Contrôler le tableau de commande
START
STOP
EN
1
Activate AC power to control
panels
2
Check to make sure conveyor is
clear of tools and personnel
3
Start conveyor by turning Start/
Stop switch to Start (
)
4
Verify belt is properly tracked
and not sagging below frame;
refer to
Belt Tension & Tracking
sec-
tion if adjustment is necessary
DE Aktivieren Sie die AC-
Energieversorgung zur Steuerung.
Vergewissern Sie sich, dass sich
keine Werkzeuge oder Mitarbeiter
auf dem Förderband befinden.
Starten Sie das Förderband,
indem Sie den Start/Stop-Schalter
auf Start schalten ( )
Bestätigen Sie, dass das Band
ordnungsgemäß die Spur hält
und nicht unter dem Gestell
durchhängt; siehe gegebenenfalls
Abschnitt Spannung &
Spurhaltung.
Repeat this procedure for the second conveyor.
Wiederholen Sie diese Schritte für das zweite Förderband.