background image

12

13

INSTALLATION AND OPERATION MANUAL SOLAR MODULES DUO-G5.X – HANWHA Q CELLS – EN

INSTALLATION AND OPERATION MANUAL SOLAR MODULES DUO-G5.X – HANWHA Q CELLS – EN

13

12

DANGER

! Risk of fatal injury due to electric 

shock! 

 

Ä

Block off the installation zone.

 

Ä

Keep children and unauthorized 
individuals away from the solar power 
system.

DANGER

! Risk of fatal injury due to electric 

shock! 

 

Ä

Ensure that modules and tools are not 
subject to moisture or rain at any time 
during installation.

WARNING

! Risk of injury due to falling  

modules! 

 

Ä

Secure modules during installation. 

 

Ä

Do not install modules in windy or wet 
weather. 

DANGER

! Risk of fatal injury due to electric 

shock! 

 

Ä

Only use dry, insulated tools. 

 

Ä

Do not carry out the installation alone.

• 

Only install undamaged modules and  
components.

 

Ä

Do not modify the module (e.g. do not 

drill any additional holes).

3.2  Preparation of installation

3 INSTALLATION

 

Ä

Maintain an interval of at least 10 mm 
between two modules.

10mm

10mm

Option 2:

 

Ä

Install the module at the 4 mounting 
points, see p. 7.

 

Ä

Tighten clamps according to  
manufacturer’s instructions.

NOTE

! Module damage may occur!

 

Ä

Do not subject modules to mechanical 
tension. Max. torsion 10 mm/m.

Option 3:

 

Ä

Install the module using mounting 

profiles, see p. 7.

Option 1:

 

Ä

Fasten the module with 4 clamps  

in the specified clamping range, 

 

see p. 7

 

Ä

Tighten clamps according to  
manufacturer’s instructions.

3.3  Module installation

3 INSTALLATION

Summary of Contents for Q.PEAK DUO-G5.X

Page 1: ...Valid for Africa Asia Europe Latin America South America Q PEAK DUO G5 X SOLAR MODULE SERIES INSTALLATION AND OPERATION MANUAL...

Page 2: ...l injury Attention Risk of serious injury or damage to property Note Risk of damage to product Safety Regulations In particular the installer as well as the operator of a module is responsible for com...

Page 3: ...ations during set up and installation Q CELLS assumes no liability on the basis of these instructions Q CELLS is only liable in the context of contractual agreements or in the context of accepted guar...

Page 4: ...g on the module are relayed to the mounting substructure Ensures sufficient rear ventilation of the module Guarantees long term stability Avoid the usage of different metals to prevent contact corrosi...

Page 5: ...ng further current blocking measures a maximum of two module strings may be operated in parallel on a single inverter or MPP tracker 2 Layout with string fuses Place fuses for each string of modules a...

Page 6: ...ecurely in cool and dry rooms The packaging is not weatherproof DANGER Risk of fatal injury due to electric shock Do not install damaged modules Inform your distributor of any damages immediately 3 1...

Page 7: ...DANGER Risk of fatal injury due to electric shock Only use dry insulated tools Do not carry out the installation alone Only install undamaged modules and components Do not modify the module e g do no...

Page 8: ...e the time intervals specified by the inverter manufacturer after switching off the inverter DANGER Risk of fatal injury due to electric shock Never open the junction box Do not remove bypass diodes D...

Page 9: ...and safe condition 4 3 Connection of modules 4 ELECTRICAL CONNECTION To avoid complex cabling arrangements it is often advantageous to rotate some modules 180 Module orientation can clearly be identi...

Page 10: ...ected regularly by certified personnel The time intervals and extent of the inspection can depend on local circumstances e g salt ammonia content in the air high humidity etc The customer operator mus...

Page 11: ...allee 17 21 06766 Bitterfeld Wolfen Germany TEL 49 0 34946699 23222 FAX 49 0 34946699 23000 EMAIL service q cells com WEB www q cells com Subject to change without notice Hanwha Q CELLS Installation m...

Reviews: