  Connect the cables  of 

lower layer 

3 batteries. Please see < Cabinet OD Cable Connection >. 

Put the separate board on the 4 stop blocks. 

Install 3 batteries on the upper layer just like under layer. 

And lock the blade bolt.  

  Connect the cables  of 

lower layer 

3 batteries. Please see < Cabinet OD Cable Connection >. 

 

  Connect the                                            cable terminals to the inverter. 

  Turn on each battery’s power switch.  

  Press Master Battery’s soft start button. Please see the product menu (capital 4.2 B).  

Lock the 6 dowels for these 3 batteries.   

Take away the 4 shield sleeves on the rails.  Put 3 

batteries on the under layer. And lock the blade bolt.  

Align the  calibration and the  battery’s hole. 

Master Battery 