4. Service and operation. 

 
4.1  Overload or short-circuit of the power supply output (SCP activation). 

            The AUX output of the PSU is protected against short-circuit by

 

PTC polymer fuse. If the power supply load 

current exceeds Imax. (110% ÷ 150% @ 25°C of the PSU power), automatic disconnection of the output voltage, 
indicated  by  switching  off  the  green  LED,  takes  place.  To  restore  the  voltage  at  the  output,  disconnect  the  load 
from the power supply output for approximately 1 minute. 
 

In  case  of  a  short-circuit  at  the  AUX,  BAT  output 

(200%  ÷  250%  load  of  the  PSU)  or  reverse  battery 

connection, the F

BAT

 fuse in the battery circuit becomes permanently damaged. The voltage restoration at the BAT 

output requires fuse replacement. 

 

4.2  Running the PSU from the battery. 

 

The power supply is equipped with the button on the PCB allowing to run the PSU from the battery, when 

needed. To do that, press and hold the 

START

 button on the unit board for 1 second. 

 

4.3  Deep discharge battery protection UVP. 

The  power  supply  is  equipped  with  deep  discharge  battery  protection  (UVP).  If  the  voltage  at  the  battery 

terminals drops below 20V±0.5V during battery-assisted operation, the batteries will be disconnected. 

The battery 

protection is on when the P

BAT 

jumper is off.

 

 

Caution.  

It is not recommended to disable UVP since deep  discharge of the batteries reduces their ability to 
store energy, their capacity and lifetime. 

 
 

4.4  Maintenance. 

All  maintenance  procedures  can  be  performed  after  disconnecting  the  power  supply  from  the  power 

network.  The  PSU  does  not  require  any  specific  maintenance;  however,  its  interior  should  be  cleaned  with 
compressed air if used in dusty conditions. In case of fuse replacement, use only compatible replacement parts. 

 
 
 
 

 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Summary of Contents for PSBS 2024B

Page 1: ...PSBS 2024B v 1 0 PSBS 27 6V 2A 2x7Ah OC Buffer switch mode power supply unit with automatic operation control EN Edition 1 from 05 05 2014 Supercedes edition...

Page 2: ...te TABLE OF CONTENTS 1 Technical description 1 1 General description 1 2 Block diagram 1 3 Description of components and connectors 1 4 Technical parameters 2 Installation 2 1 Requirements 2 2 Install...

Page 3: ...Buffer power supply PSBS 27 6V relay module MPSBS 2x7Ah PSBS 2024B MPSBS 2x7Ah 2 Buffer power supply PSBS 27 6V 4x0 5A 2x7Ah PSBS 2024B LB4 4x0 5A AWZ574 AWZ576 2x7Ah 3 Buffer power supply PSBS 27 6V...

Page 4: ...stment FBAT fuse in the battery circuit F3 15A 250V Terminals AC AC power input EPS technical output of AC power failure indication hi Z state AC power failure 0V state AC power O K PSU technical outp...

Page 5: ...Isolation transformer Printed Circuit Board see Table 1 Fig 2 TAMPER micro switch of tamper protection NC FMAINS fuse in the power supply circuit 230V T1A 250V L N power supply connector 230V AC PE p...

Page 6: ...reverse polarity connection F3 15A current limitation the FBAT melting fuse failure requires fuse replacement Surge protection varistors Deep discharge battery protection UVP U 20V 0 5V disconnection...

Page 7: ...Vibrations during operation unacceptable Surges during operation unacceptable Direct insolation unacceptable Vibrations and surges during transport According to the PN 83 T 42106 standard 2 Installati...

Page 8: ...type page 9 section 3 3 6 Use the IBAT jumper to set the maximum battery charging current taking into account the battery parameters 7 Use the PBAT jumper to set to turn on off deep discharge battery...

Page 9: ...hi Z high impedance state PSU failure can be caused by the following events Short circuit at the output Output overload DC DC voltage converter failure Under voltage protection activation LoB output...

Page 10: ...e battery The power supply is equipped with the button on the PCB allowing to run the PSU from the battery when needed To do that press and hold the START button on the unit board for 1 second 4 3 Dee...

Page 11: ...y repairs at the earliest convenienve however not later that within 14 days from the delivery to the service centre of the manufacturer 6 The repair period mentioned in item 5 may be prolonged if ther...

Reviews: