4. Connect the leads of the consumers to joints OUT + and - of the joint box on the power pack board [6].  
    (Optionally connect the MZN1 module bOUT- and load). 
5. Activate the 230 V AC power supply and insert the power network fuse protecting the transformer primary circuit 

[9]. Check the optical signalling of the power pack operation. The output voltage of the unloaded power pack is 
equal to ~ 13.8 V DC. The voltage may fluctuate from 12.8 V to 13.8 V DC during battery charging. 

6. Connect the battery in accordance with the designations [3] with colours. After this operation is completed, the 

voltage appears in the output of the power pack, which is signalled by the green diode on. 

7. Perform the power pack test checking the optical signalling [4] [5]: - the disconnection of the voltage 230 V AC 

through the removal of the fuse from the transformer socket will be signalled by the red diode going off. 

8. Following the assembly and checking the correctness of operation, the enclosure may be locked. 
 
3. Handling and operation. 
 
3.1.  Power pack operation signalling. 
The unit is equipped with the optical signalling of operation states: 

 

                    Red diode: 

 

 

 
 
 

on -the power pack is supplied with voltage 230V AC 
off -the power pack is not supplied with voltage 230V 
AC 
 
Green diode 
on – DC voltage at the output of the power pack 
off  –  DC  voltage  missing  at  the  output  of  the  power 
pack

 -  on               

   - off 

 

 

Description 

Comments 

 

 

Proper state of operation 

 

 

 

Output  overloaded  or  short 
circuited 

- check cabling and consumers 
-  if  the  battery  is  connected,  check 
battery fuse 

 

 

The 

absence 

of 

power 

supply 

from 

the 

power 

network, 

operation 

from 

battery 

- check transformer fuse 

 

 

The  absence  of  voltage  at 
the output 

- check cabling and consumers 
- check transformer fuse 
- check battery fuse 

 

flickers 

Output overloaded 

- lower the consumption of current by 
consumers 

 Tab. 4  Optical signalling. 
 
3.2. Operation from the battery. 
 

Starting the operation from the battery. 

 

The time of operation with supplies from battery depends on the battery capacity, the extent of charging 

and the load current. For example, for the typical, fully charged battery with capacity of 17 Ah and load current 2A, 
the maximum operation time safe for the battery is approximately 8h. 
 

Starting  the  power  pack  from  the  battery:  after  connecting  the  battery  in  accordance  with  the 

designations [3], the voltage appears on the output terminals of the power pack. 
 
The limitation of the battery charging current. 
The power pack is equipped with the battery charging current limitation to the value: 
- Iacc (max) = 1.4 A with unloaded power pack Iout = 0A 
- Iacc (aver.) = 0.3 A with power pack load with current Iout = 1.7 A 

Summary of Contents for AWZ 201

Page 1: ...PSU B 13 8V L 2A 1 EL TR 17Ah MC AWZ 201 v 1 0 Linear buffer type power supply EN Release 1 dated 12 10 2011 Supersedes the release...

Page 2: ...lower level of noise and shorter response time for the interference as is the case where a pulse stabilizer is applied The power pack delivers the voltage in buffer work Uout 12 8 V 13 8 V DC with the...

Page 3: ...al restart disconnection of the DC output circuit Battery charging current Iacc max 1 4 A Iout 0A 0 3A 24h I r 24h F2 Fuse in the transformer primary circuit T 315 mA 250 V Transformer primary circuit...

Page 4: ...4 Figure 3 General view of the power pack...

Page 5: ...upply circuit must be ensured Also the users should be informed about the method of disconnecting the power pack from the power supply voltage most frequently through the separation and designation of...

Page 6: ...k is not supplied with voltage 230V AC Green diode on DC voltage at the output of the power pack off DC voltage missing at the output of the power pack on off Description Comments Proper state of oper...

Page 7: ...led by the green diode going off In such a case the load should be disconnected from the output of the power pack for the period of about 1 minute 4 Maintenance All the maintenance duties may be perfo...

Page 8: ...ing of the equipment to the service centre of the manufacturer 7 The repair period mentioned in item 5 may be prolonged if there is no technical capability to carry out the repairs and in the case tha...

Reviews: