![PRx Performance Murphy Rack Fold Up Manual Download Page 5](http://html1.mh-extra.com/html/prx-performance/murphy-rack-fold-up/murphy-rack-fold-up_manual_1621956005.webp)
5
Starting Standard Installation
Standard installation is for ceilings 108” or taller. If your ceiling is shorter than
108” please see page 12 for modifications, or contact PRx Performance:
[email protected] or 1-701-566-0452
Locate Studs
1.
Fold-Up Murphy Rack with Extended Pull-Up Bar is designed to be mounted to wood studs with
standard 16” or 24” spacing, with or without drywall
2.
For mounting your rack to a wall with non-standard stud spacing, please email us at
3.
PRx recommends professional installation for mounting the wall brackets to a block, concrete, or
metal stud wall
4.
Use a stud finder to locate the rightmost stud where you intend to install the right side of your Rack
5.
Begin at the height of your lower bracket (19”)
6.
With a stud finder, locate both the left and right edge of the stud and mark them with a pencil
7.
Mark the center of the stud between the edges with a pencil
8.
Find and mark the same stud at the height of the Wall Brackets (19” and 88”)
9.
Locate and mark the remaining three studs in the same fashion. (If your studs are spaced 24”, you
will locate only two more)
Wall Bracket Helpful Tips
1.
Bracket “ears” will point downward
2.
Bracket measurements are on-center (This means measure from the middle of the hole)
3.
The distance between the two wall brackets is the
MOST IMPORTANT
measurement and should
take precedence over the bracket distance from the floor (if there is a discrepancy). For the rack to
stow properly, this measurement should be made precisely
4.
Standard studs are spaced 16” apart and correspond with the four outside holes. The center hole is
only used if studs are spaced 24”
5.
Do not over tighten lag screws. Overtightening may strip the pilot hole